Photos from ten years ago: December 2014

It’s the last day of the year so what better time than another instalment in my photos from ten years ago series – this time it is December 2014.

On the train

Yes, still on the Regional Rail Link topic – Ballarat and Bendigo trains now had their own tracks through Footscray to Sunshine, along with their own next train displays located away from the ones showing suburban trains.

 V/Line only PIDS added to the concourse at Footscray station

But for now Geelong line services were still running along the Werribee line. Here we see a N class locomotive hauled train passing through Williams Landing.

N462 leads a down Geelong service through Williams Landing

A VLocity train passing through Laverton station.

VLocity 3VL50 leads a down Geelong service past an up Siemens train at Laverton station

And another passing through the platforms at South Kensington.

VLocity 3VL40 leads an up Geelong service along the suburban tracks at South Kensington

Which then took the crossover at the city end of the station to access the new V/Line tracks towards Southern Cross.

Up Geelong service on the suburban lines at South Kensington crosses onto the RRL tracks towards Southern Cross

Freight trains

A decade ago Pacific National still had the contract to transport grain by rail to the flour mill at Kensington. Southern Shorthaul Railroad won the contract in November 2017.

XR551 and X41 bring the loaded Kensington grain service into the goods siding at Melbourne Yard

Meanwhile down at North Geelong Yard Pacific National was busy scrapping surplus wagons – the bulk of which once transport freight that has been lost to road.

Scrapping of surplus Pacific National wagons at North Geelong Yard

Down around Geelong

The North Geelong B signal box was still hanging around a decade after it had been decommissioned in 2005, and surprisingly it hung around almost a decade longer – eventually being demolished in May 2022.

A decade of decay since decommissioning

While down in Grovedale money was getting spent on Baanip Boulevard, with a new bridge being built over the railway to link the Geelong Ring Road to the Surf Coast Highway.

Bridge piers in place for Baanip Boulevard crossing over the railway

And down at North Shore even the dive of a station was getting some attention – new asphalt!

Platforms 1 and 2 freshly resurfaced

Ding ding on the trams

Remember the ‘Melbourne Star’ observation wheel? This tram was advertising it, before the operator went broke in 2021.

B2.2100 advertising 'Melbourne Star' has now caught up on the timetable, and is ready to depart Camberwell Junction with a route 75 service towards the city

But a tourist icon that people actually patronised was the Colonial Tramcar Restaurant – it ran until 2018 when their restaurant trams were kicked off the Yarra Trams network due to safety concerns.

SW6.935 and SW6.964 lead the lunch run at the corner of Spencer and Collins Street

Another safety concern that is having to dodge cars to climb onboard tram at South Yarra station. The platform stop there wasn’t opened until 2021.

D1.3518 picks up outbound route 8 passengers at South Yarra station

Another crappy tram stop was the one at La Trobe and Swanston Street – on this December afternoon it was overwhelmed by a crowd of RMIT graduates spilling out onto the road. Platform stops were not provided along La Trobe Street until July 2024.

SW6.881 arrives to hoards of RMIT graduates at the corner of La Trobe and Swanston Street

And continuing on that theme, now we’re at Collins and Queen Street – closed in 2015 following completion of a new platform stop at Collins and William Street.

C.3003 heads west on route 109 at Collins and Queen Street

Another stop to close being the one for southbound route 96 passengers at the corner of Spencer and Flinders Street.

'Stop closing' notice for southbound route 96 passengers at the corner of Spencer and Flinders Street

Works about to start on new platform stops at Batman Park a short distance to the south.

D2.5014 stops for passengers at Batman Park on a southbound route 96 service

A few buses

A decade ago route 400 between Sunshine and Laverton was operated by plain white liveried buses – an artifact of the shared operation of the route between Westrans and Sita. Today the operations are now CDC Melbourne and Transit Systems, and the white buses are gone – they’re mostly PTV orange, with the exception of a few buses still in the old poo brown Sita corporate livery.

Plain white liveried Sita bus #130 rego BS00BO waits for route 400 passengers at Sunshine station

Another oddball bus was the British-built Optare Solos used on the SkyBus hotel shuttle service around the Melbourne CBD. Later branded as ‘SkyBus Link’, the service was discontinued in 2020 thanks to the Covid-19 pandemic, and never restored.

SkyBus hotel shuttle #36 rego 7109AO - this weird looking thing is a British-built Optare Solo

And the last bus is a Designline ‘bubble’ bus running on route 903 along Bell Street in Coburg.

Transdev bus #637 rego 7260AO heads west on a route 903 service along Bell Street in Coburg

Stuck in traffic waiting at the level crossing with the Upfield line – which was removed in June 2020.

Shattered bits of orange, red and clear plastic mark multiple crashes at the Bell Street level crossing in Coburg

Ticketing bits

Down in Geelong it was once possible to buy a ‘Short Term Ticket‘ from bus drivers rather than use a Myki card – an option removed in April 2013.

'myki is the only way to travel' sticker on the side of a McHarry's bus

While in the lead up to the November 2014 election both parties promised to cap Melbourne suburban travel to zone 1 prices, and introduce the ‘Free Tram Zone’ in the CBD.

PTV flyers onboard a tram promoting the 'Free Tram Zone'

Both starting from 1 January 2015.

'Free Tram Zone from 1 January 2015' and 'This stop is outside the Free Tram Zone' notice outside Parliament Station

But don’t think they’re giving you something for nothing – PTV was simultaneously running yet another fare evasion campaign.

Transdev / PTV branded fare evasion advertisement on the rear of a bus

As well as promoting free travel on Christmas Day.

PTV advertisement for free travel on Christmas Day at Melbourne Central station

Car parking

What’s a worse use of prime CBD land than a ground level car park? This is the ‘Golden Square’ car park at 217 Lonsdale Street, which is still a car park today.

'Golden Square' car park at 217 Lonsdale Street

And this is the ‘Safe City Car Park’ at 132 Little Bourke Street in Chinatown – which has since been turned into a pop up event space.

'Safe City Car Park' at 132 Little Bourke Street

And finally – a power station

Here we are at the main gate to Anglesea Power Station.

Main gate to the Anglesea Power Station

Located in the middle of the Anglesea Heathlands.

Looking down on the Anglesea Power Station from the lookout atop the adjacent coal mine

Next to a brown coal mine.

Dump truck returns for yet another load of overburden out of the open cut coal mine at the Anglesea Power Station

Opened back in 1969 to power Alcoa’s Point Henry smelter outside of Geelong, the smelter was closed down in July 2014 but the power station remained open pending a new owner, before it too was shut down in August 2015.

Footnote

Here you can find the rest of my ‘photos from ten years ago‘ series.

Cooked next train displays at Southern Cross Station

It’s a hot summer day and you just want to get home, so you walk into Southern Cross Station to catch a train – only to be greeted by a failing wall of next train displays.

'Gladiator II' advertising covers Southern Cross Station

Yep, it’s cooked

Three out of the seven displays are barely visible – leaving the next seven V/Line departures MIA, along with the entire list of V/Line arrivals, and all services on the Cranbourne, Pakenham and Frankston lines.

Three out of seven next train displays out of service due to overheating at Southern Cross Station

But luckily you turn around and find a second set of screens – only to discover half these ones are also broken – you can now see the Cranbourne, Pakenham and Frankston lines; and the V/Line arrivals are nice and bright; but the Lilydale, Belgrave and Glen Waverley line are gone.

Three out of seven next train displays out of service due to overheating at Southern Cross Station

And the next seven V/Line departures – if you squint hard, you might just be able to read them on the faded screen.

Three out of seven next train displays out of service due to overheating at Southern Cross Station

And don’t hope on walking over to the platforms either – the screen at the top of platform 11 and 12 was also hardly visible.

Train display at Southern Cross Station platform 11 and 12 hardly visible thanks to the screen overheating

As was the one above platform 15 and 16.

Train display at Southern Cross Station platform 15 and 16 hardly visible thanks to the screen overheating

But why?

The reason for the screens not working? The screens aren’t broken outright, as they work most of the time.

Half of the suburban next train displays have come back, but the other half are still dead at the main entrance to Southern Cross Station

The clue being in tiny text in the corner of the screen – ‘TEMPERATURE WARNING!!’. I photographed the failing screens on December 5th, when the top temperature was 33.2 °C, and that was enough for the the screens to be unable to cope.

'TEMPERATURE WARNING!!' message on the PIDS at Southern Cross Station

I found a similar warning on one of the platform screens on February 4th – when the top temperature was 37.5 °C.

'TEMPERATURE WARNING!!' message on the PIDS at Southern Cross Station

So in theory a simple fix – but the management at Southern Cross Station can’t even change a light bulb.

And they aren’t that old

You might point the finger at the screens being old, but that isn’t exactly true – for years Southern Cross Station used a ‘temporary’ array of CRT television screens to display the next suburban train departures.

Next train display at Southern Cross with 'Keilor Plains' as the terminus of the Sydenham line

The permanent LCD screens not being switched on for suburban trains until March 2009.

Suburban train displays finally working after three years

Allowing the ‘temporary’ screens to be covered up.

'Temporary' suburban CRT next train displays finally covered up, over 3 years since the supposed 'completion' of the station. How long until they actually go?

Until they were finally removed in April 2010.

Finally removing the 'temporary' CRT next train displays, after how many years?

And the LCD screens didn’t last long anyway – they were removed in November 2012 for “maintenance”.

LED screens outside the Bourke Street entrance to Southern Cross Station out of service for maintenance

Out of service from November 12 to December 23 – that’s 41 days to change eight screens!

Out of service from November 12 to December 23 - that's 41 bloody days to change eight screens!

Footnote: another other things cooking in the heat

Melbourne’s Comeng suburban trains from the 1980s also once had a reputation for failing in the heat.

Alstom Comeng 640M arrives at Camberwell on the up

The air conditioning failing once the temperature reached 35 degrees.

Air conditioning unit on a Comeng - note the cutout for the guards periscope

So after a spate of failures during the summer of 2008-09, the decision was made to upgrade the air conditioning units fitted to said trains.

Different style ground plane antenna on the roof of Comeng 301M

And lo and behold – they’re just as reliable as newer trains in hot weather.

Bolt down bike hoops are useless

When you go to lock up your bike, one thing to keep an eye out for is bolt down bike hoops.

Mismatched bike hoops at Sunshine station after someone unbolted them to steal the bikes locked onto them

As all a bike thief needs is a shifter to unbolt it from the ground.

Bike hoop dumped at Sunshine station after someone unbolted it to steal the bike locked onto it

And ride away with the bike that was locked to it.

Exposed bolts mark where someone unbolted a bike hoop at Sunshine station to steal the bike locked onto it

It’s the reason why they say put your bike lock through the rear wheel *and* the frame.

A U-lock can go around the rear rim and tire, somewhere inside the rear triangle of the frame without looping it around the seat tube: the wheel cannot be pulled through the rear triangle. A lock which passes around a rim makes the bicycle unrideable even if the object it is locked to can be broken or disassembled.

Because cutting up a bike defeats the point of trying to steal it.

Some people will object that felons might cut the rear rim and tire to remove a lock. This just doesn’t happen in the real world. It is possible to cut the rim with a hacksaw, working from the outside to the inside, but first, the tire must be removed or cut through. It would be a lot of work to steal a frame without a usable rear wheel, the most expensive part of a bike after the frame.

What makes these particular bike hoops egregious was that they installed as part of the Regional Rail Link project a decade ago along with the concrete path, so it isn’t even “boring holes was too hard” – they could’ve embedded the bike hoops into the concrete when pouring it.

Room for the future RRL tracks to pass beneath the new overhead concourse

And retrofitting concreted in bike hoops isn’t that hard – you just need a core drill.

Drilling holes in bluestone pavers to install new bike racks

There is your hole.

Drilling holes in bluestone pavers to install new bike racks

Pop out the paving.

Drilling holes in bluestone pavers to install new bike racks

And you’re all done.

A year after the City of Melbourne said they would move them, the bike hoops at William and Bourke Street are now parallel to the kerb, instead of blocking the footpath

And it’s not the first time

Did you notice anything odd about the row of bike hoops in my lead photo?

Mismatched replacement bike hoop at Sunshine station

Yes, they’re all brushed metal except for one with a galvanised finish – presumably a replacement after another bike thief unbolted the previous hoop.

Then and now along the West Gate Freeway

Today we’re taking a ‘then and now’ tour over the West Gate Bridge.


PROV image via West Gate Tunnel Project

Approaching the Lower Yarra Freeway

We start on the Prices Highway way back in 1969, one mile away from the junction with what was then called the ‘Lower Yarra Freeway’.


VicRoads photo, via West Gate Tunnel Project

And the view today – the ‘Lower Yarra Freeway’ is now called the West Gate Freeway, the Princes Highway via Footscray is now the secondary route, the two lanes have doubled to four, and the Western Ring Road has been added to the junction.

And the changes can also be seen at the freeway junction itself.


VicRoads photo, via West Gate Tunnel Project

Dohertys Road over the freeway having been duplicated in 2021, with more lanes underneath to come as part of the West Gate Tunnel Project.


Google Street View

On to Williamstown Road

We now move onto this 1970 view from the West Gate Freeway at Williamstown Road – an ‘End Freeway’ sign attached to the footbridge – the West Gate Bridge having collapsed during construction on 15 October 1970, with the death of 35 workers.


VicRoads photo, via West Gate Tunnel Project

And the view today with a completed bridge, and changes thanks to the West Gate Tunnel Project – tall concrete noise walls, the Woduyullul Parring footbridge completed in 2020 to replace the previous open air footbridge; and small footprint steel monopole towers that replaced the traditional lattice towers supporting the 220 kV transmission lines.


Google Street View

Onto the bridge

No traffic in this view of the West Gate Bridge before it was officially opened.


VicRoads photo, via West Gate Tunnel Project

But the main difference today – the suicide barriers hurried erected in 2010 after years of the government refusing to do so.


Google Street View

Check out the view!

And here is the view from the top, looking over to the Melbourne CBD.


VicRoads photo, via West Gate Tunnel Project

With 40 years of development filling out the skyline.


Google Street View

And down below

Headed through Port Melbourne

We start off at Graham Street interchange in Port Melbourne, with this 1983 view looking west towards the West Gate Bridge.


VicRoads photo, via West Gate Tunnel Project

And the view today – the trees are taller and the ‘UFO’ lights are gone, and more importantly, Graham Street doesn’t traverse the bridge anymore. Instead the bridge forms the connection between the Bolte Bridge and the West Gate Freeway, with the Graham Street severed in 1997 so that construction of the CityLink project could proceed.


Google Street View

And over South Melbourne

Now we are in 1987, and it is opening day of the first stage of the elevated West Gate Freeway extension through South Melbourne to St Kilda Road.


VicRoads photo, via West Gate Tunnel Project

While the view today shows the connection through to CityLink completed in 2000, and additional lanes added in 2011 as part of the Monash–CityLink–West Gate Upgrade project.


Google Street View

Footnote: a bonus bridge

And here’s a 1971 photo of workers having a smoko beneath the Grieve Parade overpass.


VicRoads photo, via West Gate Tunnel Project

In 1991 the original bridge was widened as part of the duplication of Grieve Parade – the original two lane span being joined by another four lane bridge to the west side.


Google Street View

But the heavier trucks of today were too much for the original bridge to handle, and so in January 2021 the spans were demolished as part of the West Gate Tunnel project.


Google Street View

The eastern half rebuilt with stronger concrete super-T beams, and the earthen embankments cut back to fit more traffic lanes beneath.


Google Street View

The saga of lifts at Watergardens station

For something that was built from scratch 20 years ago, the accessibility issues at Watergardens railway station on the Sunbury line stand out – this is the story of the lifts that didn’t work, and the effort that went into fixing them.

Big crowd waiting for a citybound train at Watergardens station

In the beginning

For years Sydenham station was a wayside stop on the empty plains north-west of Melbourne enroute to Bendigo.


SLV photo H1077

But the suburbs of Melbourne eventually grew north to Sydenham, and so in 2000 the decision was made to extend suburban trains from St Albans five kilometres north to a new station called ‘Watergardens’.


Weston Langford photo

Which opened in 2002.

Plaque marking the opening of Watergardens station and the electrified Sydenham line

The new terminus was well provisioned for a terminus station – three platforms, with centre turnback for terminating trains.

Centre island platform at Watergardens station

Sidings at the down end for stabling trains to form peak services.

Siemens train shunts out to the yard at Watergardens

Three lifts – one of the street on both sides, and a third to the central island platform.

Eastern entrance to Watergardens station

With stairs in parallel.

Steps between platform and concourse at Watergardens station

However the footbridge across the tracks is narrow compared to what stations have today.

Footbridge across the tracks at Watergardens station

And the lifts were undersized compared to current standards – of 12 person capacity rather than 18.

But the lifts don’t work

As Watergardens station aged, the lifts weren’t exactly the most reliable – from 2016:

A malfunctioning lift at Watergardens train station that reportedly breaks down nearly every second week, on average, is likely to be replaced.

Western Metropolitan MLC Bernie Finn told state parliament recently the Watergardens lift had broken down 43 times over the past two years, and sometimes took a week to fix.

“For people to have to wait for up to a week for a broken down lift to be fixed seems to me to be quite insane. That is just ridiculous,” he said. “It is a major concern, particularly for people with disabilities and for elderly people.”

Public Transport Victoria and Metro Trains have been forced to provide maxi taxis for special needs commuters, who could not access the train to get to doctors’ appointments.

Mr Finn has also called for a second ramp to be built to service both sides of the station.

“I find it just astonishing that we have a lift there that has broken down so often. There is only one ramp for people to use, and it is on the opposite side of the platform,” he said.

“I just do not understand how the PTV could allow such a situation to exist.”

A PTV spokesman said it would continue to provide “alternative transport arrangements” for passengers when lifts are out of order.

“PTV is committed to finding a permanent solution for passengers – which at this stage could involve replacing the lifts,” he said.

Lift failures rendering stations inaccessible being the reason why the trio of stairs, lifts and long zig-zagging ramps with a DDA compliant 1 in 14 gradient has became the standard at new and upgraded railway stations in Melbourne from 2013.

Looking up the long ramp back to the concourse

But in the case of Watergardens station it was too late for that, so the only option was to upgrade the control and power supply systems for the existing lifts to improve their reliability – requiring one outage from 1 to 5 May 2017, and a second from 18 September to 3 November 2017.

And spending the big money

But even upgraded lifts can still fail, so in 2016 PTV commissioned Jacobs Group to study possible options to bring Watergardens station up to current standards, and provide a redundant method of access if the existing single lift to a platform failed.

They looked at going under, over and through the tracks. As you might expect, building a new level crossing got knocked on the head pretty quickly, and going under option was less than salubrious, so also got knocked out.

This left three options to upgrade the existing overpass – duplicating the three existing lifts, providing a ramp beside each lift, or a hybrid option with a additional lift to the island platform and two ramps to the street entrances.

Fitting in the new ramps on the street site was easy.


Artist’s impression, Jacobs 2016

But the island platform was more constrained, with a DDA compliant ramp taking up much the space at the Melbourne end.


Artist’s impression, Jacobs 2016

The Jacobs report also looked at the costs of the three options:

3.2 Constructability and Whole of Life Costings
An estimate of the turn out and life cycle cost for the 3 options – out to 30 years – is attached as Appendix D.
In precis, the full lifts option is the cheapest in the short term, the full ramps the most expensive:
Option 1 – All Lifts $5,276,700.00 – immediate Capital Construction Cost.
Option 2 – 2 ramps + 1 lift $5,595,000.00 – immediate Capital Construction Cost.
Option 3 – All ramps $6,568,200.00 – immediate Capital Construction Cost.

When factoring in the costs to service and maintain each option for 30 years (non-discounted cashflow) the costs become:

Option 1 – All Lifts $9,868,230.00 – adding $4,591,530.00 (non-discounted $s) in costs over 30 yrs.
Option 2 – 2 ramps + 1 lift $7,661,793.00 – adding $2,066,793.00 (non-discounted $s) in costs over 30 yrs.
Option 3 – All ramps $7,632,994.00 – adding $1,064,794.00 (non-discounted $s) in costs over 30 yrs.

For the first 10 years Option 1 has the lowest WOL cost.
Between year 10 to year 29 Option 2 has the lowest WOL cost.
After 30 years Option 3 has the lowest WOL cost.

Surprisingly the lift option was cheaper to build initially, through obviously the ramps became cheaper once ongoing maintenance costs were included.

Decision time

The 2018-19 State Budget committed $8.9 million to upgrade Watergardens station, with community consultation taking place in July 2018.

'We're building new lifts at Watergardens station' poster on the concourse

But there was a problem – the preferred option was installing additional lifts, but the PTV Network Technical Standards at the time required lift, stairs and a ramp for a vertical change of 5.6 metres – and so a waiver was required to provided a second lift, as well as to infringe on the minimum platform width where the new lift would land on the island platform.

However a waiver was granted, and work started on the project in early 2021.

The new lifts being located in plain grey towers, beside the existing brick ones.

Three new lifts in place at Watergardens station, providing redundant access to all areas

An additional lift added at the end of the western entry.

Second lift added at the western entry to Watergardens station

And to the eastern entry.

Second lift added at the eastern entry to Watergardens station

While the additional lift to the island platform was snuck in beneath the existing concourse.

Siemens 807M arrives into Watergardens on the up

The stairs to the platform rebuilt.

New stairs to Watergardens platform 2 and 3, relocated to make way for the second lift

To pass around the new lift shaft.

Second lift added at Watergardens platform 2 and 3

Which looks like it was always there.

Contactless lift at Watergardens platform 2 and 3

PTV having this to say about the upgrade.

We have opened three new lifts at Watergardens Station to help people move around the station precinct and catch the train more easily.

This is part of the Public Transport Accessibility Improvements Program, which sees several metropolitan train stations upgraded to comply with current access guidelines for people with disabilities.

The new lifts feature:

  • more space to increase lift capacity and allow for social distancing
  • improved lighting
  • a back up power supply, making them more reliable and avoiding breakdowns
  • improved security with new CCTV coverage and windows
  • more open design than the existing lifts with partially transparent lift walls.

Other completed works at Watergardens Station:

  • We have increased the number of wheelchair accessible parking spaces in the Sydenham Road car park from five to nine.
  • A back up power generator has been constructed to help power the lifts and station in the event of a blackout.
  • Six extra CCTV cameras have been installed to cover blind spots around the stairs.
  • Toilet refurbishments have been completed on the central platform and concourse to improve passenger amenities.
  • New tactile ground surface indicators have been installed on all three platforms to improve accessibility.

A lot of work for a railway station only 20 years old!

Footnote: ramps vs lifts

Back in 2016 the Level Crossing Removal Authority also had to fight to avoid building massive ramps as part of the Mernda rail extension, but since then it seems to be a non-event – most new stations built since then feature dual redundant lifts to each platform, rather than ramp and a lift.

Pair of operational lifts at Pakenham platform 1

Footnote: platform extensions

The 2016 Options Report by Jacobs touched on the need for platform extensions at Watergardens station for the upcoming fleet of High Capacity Metro Trains, and flagged at changes at the city end would be the logical option.

1.5 Provision for other works – Future 10-car HCMT

Possible options should consider other works that may occur at or around the station in the future. The most important of these – in fact, the only one known to Jacobs – is the platform extensions for the new 10-car High capacity Metro trains (HCMT).

Currently the 3 platforms are 160 m long. The island platform is approximately.8.9 m wide at the down end; tapering on the Platform 3 side to c.7 m at the up end. All platforms will require an extension of 70m to bring them 230 m and, depending upon where this extension occurs, Platform 3 may need straightening.

Informal advice from PTV indicates that it is likely that it would be simpler and less costly to extend the platforms toward the city.

Jacobs’ own study of aerial photographs indicates that the gates to the stabling yards down from the station are c. 200 m from the NW end of the platform and that there are at least 7 sets of points in this area. The corridor to the SE is significantly less congested with 5 sets of points within c.250 m of the station after which it appears to be completely unencumbered until it reaches the next station at Keilor Plains.

For these reasons it seems most likely that the platform extensions would occur to the SE (up end); widening Platform 3 to remove the existing taper to provide an island of consistent width for its full length. Although the platform extension has no immediate bearing on the provision of secondary (or contingency) means of access to and from the station, as the widening would create additional space on the platform that would ease a pinch point in one of the options (see below), an up end extension to the platforms has been presumed in the development of the options..

And then look at what happened in 2022 – the entire lead into the yard at the down end of Watergardens was rebuilt.

Platform extensions at the down end of Watergardens station awaiting a concrete pour

Platform 1 extended by 15 for a 7-car HCMT.

Platform extension at the down end of Watergardens platform 1

And platform 2 and 3 extended by an even shorter 12 metres.

Platform extension at the down end of Watergardens platform 2 and 3

They also completed a major track slew at the down end of the yard at Watergardens, taking the sidings from 329 metres (two 6-car trains) long to 560 metres (three 7-car trains) long.

Siemens 839M and 765M stabled at the down end of Watergardens siding A

Footnote: the gory technical details

First – the options study by Jacobs.

Watergardens Accessibility Study
Options Study
December 2016

Watergardens station was designed and constructed between c. 2000 – 2002. The station was officially opened in January 2002.

The design provided for a single lift and stair access only to and from the island platform and the adjacent streets on either side of the station. However, the lifts have proved to be unreliable and, for those unable to use the stairs, access and egress to and from or across the station from either side has been made difficult.

With this in mind, PTV commissioned Jacobs to carry out an Options Study to draw out such options as might exist to provide a secondary means of access from one side of the station to the other and to the station’s central island platform for those unable to use a flight of stairs

The station contains 3 platforms – Platform 1 to the NE on the shopping centre side of the line and platforms 2 and 3 forming an island platform. Access to Platform 1 is made by one of two sets of stairs – one of 12, the other 13 risers – or one of two ramps – rising from the kerbside footpath. From the level of Platform 1 access is provided to the concourse level (c. 5600 mm above Platform level) by means of a lift or stair of 33 risers (two flights – of 17 and 16 risers).

From the SW side of the line, access to the station is made at concourse level. This is some 7000 mm above the pavement level, with access provided by means of lift or stairs. This stair consists of two flights – of 20 and 21 risers – 41 risers in all.

From the concourse access is provided to the island platform by lift and stair of two flights.

Looking at going under, over and through the tracks.

2. Options
Based upon the limitations noted above, there are three basic approaches – to cross the rail line / gain access to the platforms:
– At grade
– Under the permanent way
– Over the permanent way

As you might expect, building a new level crossing got knocked on the head pretty quickly.

2.1 Options – At-grade

Whilst recognising that both pedestrian and vehicular at-grade crossings both are, as a matter of PTV guidelines, no longer considered suitable, for completeness the possibility of at-grade options has been considered.

An at-grade point of egress has been provided at the down (NE) end of the island platform. This was previously used to provide emergency egress for the mobility impaired from the platform to the kerb-side on Sydenham Road, but the practice has since been discontinued. Presently, in the event of a lift failure, mobility impaired patrons are re-entrained and taken to the nearest accessible station from whence they are returned to Watergardens by taxi.

The ramp is still used by the Train drivers to access the stabling yard down line from the station.

In discussion with PTV and MTM at an initial Stakeholder consultation, it was agreed, for the above reasons and more, that an at-grade option is not feasible and was not pursued as a viable design option.

The going under option was less than salubrious, so also got knocked out.

2.2 Options – Under the permanent way

One underpass option was considered.

This is based upon using ramps of a maximum length of 6000 mm at an inclination of not more than 1:14 (one metre rise over 14 metres of length). Landings of not less than 1200 mm length are provided between each section of ramp. Larger landings are provided at changes in direction.

The scheme provides a straight ramp (of 10 x 6000 mm sections) descending from ground level adjacent the existing lift and stairs on the SW side of the station to a horizontal underpass lying c. 5600 mm below the level of the platform.

This ramp runs through the area currently used as a retention basis for storm water runoff from the adjacent carpark.

From the bottom end of this ramp, the underpass runs under Sydenham Road and the up end of the platform to emerge on the NE side of the lines with a switchback ramp (of 8 x 6000 mm sections) in an open area between the Telstra communication tower and existing station ramps. This delivers users c.60 m to the south of the existing station entry. The underpass is c. 50 m long.

A third ramp (of 13 x 6000 mm sections) runs from the mid-point of the underpass to deliver patrons to the far SE (up) end of the island platform.

The overall length of ramps and underpass is c. 190 m. There is a further c. 95 m of ramp from the underpass to the island platform.

In discussion with PTV and MTM at the initial Stakeholder consultation, it was agreed by all that due to the excessive ramp length required, particularly for the elderly and people with a disability, site drainage issues, issues surrounding potential local contaminated soil and the potential public safety risks associated with a long, unsupervised tunnel that this option was unfeasible and not to be pursued further.

Leaving options to upgrade the existing overpass.

2.3 Options – Over the permanent way

Three approaches suggest themselves to provide access over the permanent way:
• An all lift option – duplicating the three existing lifts
• An all ramp option and
• Hybrids of the above – the main version involving two external ramps with a lift to access the island platform

2.3.2 Three Additional Lifts

Duplicating the existing lifts is the most obvious approach to providing redundancy / contingency access to and across the station. There is some flexibility with the placement of these lifts but in each case, one position generally seems to recommend itself over the alternatives.

At the station entrances, new lifts can be located adjacent each of the existing entrance lifts. Subject to the final geometry of the lifts to be used, there appears to be sufficient space at both ends of the existing concourse to land a second lift.

Access to the island platform is more constrained. There does not appear to be anywhere adjacent the existing lift or on the existing concourse where a new lift could be placed without significant and deleterious effect upon the existing flow and function of the concourse.

The only suitable place is on the platform – on the up side from the stairs. To accommodate this, the existing concourse – complete with its glazed screen is to be extended. The concourse would extend to fill in the spaces on either side of the existing stairs and thence extend as a “U” to the new lift.

The new lift placement would require the relocation of the existing platform canopy and its associated furniture.

2.3.3 Additional Ramps and Central Platform Lift

After an all Lifts option, the next option is to replace lifts with ramps where these might be done easily i.e. outside the limits of the station but to keep a lift to the island platform.

The option is based upon providing two 1 in 14, 1.8m wide ramps – one on either side of the station – linking these into the existing stairs. This was a part of the original design – allowing the stairs and ramps to sit side by side – sharing the same landings at ground / platform and concourse levels.

As in the all Lift Option, the lift option requires an extension of the concourse and reconfiguration of the canopies.

On the NE (shopping centre) side, the ramp consists of 13 x 6 m sections for an over-all rise of c.5600 mm from platform level to the concourse. The rise from the street to the platform is provided by existing ramps. On the SW side, the ramp rises c. 7 m – 17 x 6 m sections – and is over 125 m in length.

2.3.4 Additional Three Ramps

The third option is that of 3 ramps consisting of a ramp at either station entrance (as per Option 2) and a third ramp on the island platform.

To install the required ramp on this platform at least one switch back is required. (The platform is not quite long enough to accommodate a single length ramp – being short by perhaps 3 m plus ramp run-off.) The difficulty that emerges is to maintain a 1.8m clear width between handrails on the ramp (and a zone on either side for screening on it) and maintain clearances at platform level to the coping.

In the layout as proposed, as the platform tapers a pinch point is reached where the width to the coping must be reduced to c. 3.1m. This “pinch” decreases as the ramp drops to platform level – opening out to c. 3.6 m at platform level.

The report also covered the suitability of lifts in general.

The current 12 person public lifts are smaller than is required by the current standard and are subject to vandalism.

Lift reliability is currently a problem because they operate publicly for 24 hours and are the only method of DDA entrance to and egress from the platform.

The additional lifts proposed in Option 1 & 2 will be larger 18 person lifts (3.5 x 3.5m footprint) and compliant with current design standards.

Discussion took place during the initial stakeholder meeting about whether new lifts should be introduced considering the maintenance issues associated with the existing 24 hour public use. The example of Coolaroo Station was given as a successful case where the introduction of duel public lifts works successfully. In addition, it was suggested that the majority of vandalism occurred within working hours as opposed to at night.

The current lift renewal programme was also discussed. It was noted that it could be 18 months before the existing lifts will be replaced and that some action will be required to improve reliability in the interim.

It was also noted that during the replacement of the existing lifts a means of temporary alternative access and egress will need to be provided. No solution to this was suggested, but Jacobs notes that it may be preferable to defer the upgrade of the existing lifts until after the installation of the alternative means of access considered in this study.

During the stakeholder meeting it was noted that by introducing ramps; the lifts may be turned off after hours, reducing maintenance and safety concerns, noting also that ramps are easier to install and of low maintenance comparatively to lifts. Ramps are likely to be less expensive over the long term however this is sensitive to maintenance costs.

Discussions took place around what would happen if no ramp upgrades occurred and lifts were closed at night. It was decided that removing an amenity that was previously provided would cause complaints and is not a suitable option.

Turning Lifts off after hours was generally accepted as an option that could be explored further.

And the costs of the three options:

3.2 Constructability and Whole of Life Costings
An estimate of the turn out and life cycle cost for the 3 options – out to 30 years – is attached as Appendix D.
In precis, the full lifts option is the cheapest in the short term, the full ramps the most expensive:
Option 1 – All Lifts $5,276,700.00 – immediate Capital Construction Cost.
Option 2 – 2 ramps + 1 lift $5,595,000.00 – immediate Capital Construction Cost.
Option 3 – All ramps $6,568,200.00 – immediate Capital Construction Cost.

When factoring in the costs to service and maintain each option for 30 years (non-discounted cashflow) the costs become:

Option 1 – All Lifts $9,868,230.00 – adding $4,591,530.00 (non-discounted $s) in costs over 30 yrs.
Option 2 – 2 ramps + 1 lift $7,661,793.00 – adding $2,066,793.00 (non-discounted $s) in costs over 30 yrs.
Option 3 – All ramps $7,632,994.00 – adding $1,064,794.00 (non-discounted $s) in costs over 30 yrs.

For the first 10 years Option 1 has the lowest WOL cost.
Between year 10 to year 29 Option 2 has the lowest WOL cost.
After 30 years Option 3 has the lowest WOL cost.

Next – the PTV Network Technical Standard Waiver.

PTV-NTS-002-W004 – Watergardens Dual Lift to Island Platform

Currently the central island platform (Platforms 2 and 3), Watergardens Station has DDA-compliant vertical transport with lifts and stairs, but the lifts have no operational redundancy. In the case of a lift failing, passengers with a DDA-accessible requirement would need to travel to the next accessible station and be provided with a taxi to return to Watergardens.

Up until 2017, lifts at Watergardens have not been reliable with many people having to travel to other stations to maintain access. In 2017 lifts at Watergardens were upgraded to increase their reliability lack of redundancy remained an issue.

Recently the State budget provided $8.9 million funding to provide for 3 lifts and increased concourse area at Watergardens Station. Design options for Watergardens were canvassed in a report by Jacobs on behalf of PTV: Watergardens Accessibility Study – Options Study – 02 December 2016.

Compared with the current arrangements, accessing the island platform (Platforms 2 and 3) requires a vertical change of about 5.6 metres above the platform. Normally this would trigger the need for a lift, stairs and a ramp (as opposed to two lifts).

However, providing a switchback ramp here with appropriate concourse modification, has been assessed as being a higher risk than providing a second lift with concourse modification. Providing a continuous grade (non-switchback) ramp would require platform extension, which would trigger expensive track work and will not be considered.

A Waiver is required to be provided to allow two lifts to be used in lieu of a lift, stairs and a ramp. Compliance with minimum platform width standard (MTM Structure and Facilities Standard (MCST 020 100-01)) cannot be achieved with either ramp or lift solutions. Ramp non-compliance would occur over a much longer length of the platform than a lift. This clearance will be subject to a Safety In Design Review once design has been completed. The lift non-compliance will need to be assessed further during detailed design and a potential subsequent MTM standards waver, separate to this application will need to follow process.

And the project requirements document.

Client Requirements Document
Watergardens Station Accessibility Upgrade
December 2018

As a part of the Public Transport Accessibility Improvements Program, several stations within the Metropolitan train network have been stated to receive upgrades in order to achieve compliance with current access guidelines for people with disabilities. Watergardens Station is identified as being in critical need of accessibility improvements. The reasons for this are summarised below:

• The current station has been prone to frequent lift failures causing reduced access to Patrons/Passengers and increased travel times. This has been attributed to unreliable lifts, lack of backup power systems and vandalism.
• With the concourse between the car park and shopping centre serving as a 24×7, primary access path for station patrons and general public alike, reliability issues with the lifts and vandalism lead to accessibility issues.
• The current issue is exacerbated as the lifts in the station are not complaint with DSAPT standards which raises major concerns with regards to safely accessing and moving casualties from the station.

There are some unpleasant customer experience complaints (from Jan 2017 to Oct 2018) against Watergardens Station regards to the DSAPT non-compliance station amenities. These complaints were lodged through MTM customer feedback system.

The main complaint topic is expressing the unpleasant reliability of the existing station lifts and inconvenience to enter and exit platforms when the lift/lifts are out of service. The other streams, one is about no level access or poor direct assistance for mobility impediment passenger boarding, and the other one is about inefficient/misleading notification to passenger with impediment.

If the concourse is inaccessible, the closest access path to cross the tracks is located about 750 meters on the Down side of the station and the other access is located about 1.5km from the station on the Up side of the station. There is no backup power supply for the existing three lifts.

友情链接: 极速赛车官网168开奖-168官网开奖记录|极速赛车开奖记录 - 开奖查询结果 极速赛车官方,澳洲幸运5,8,10,幸运飞艇官网,168飞艇,澳门彩,河内5分彩 澳洲幸运5开奖官网直播结果+历史号码查询|澳洲幸运2025官方开奖记录,开奖结果体彩网 168网官方开奖结果_幸运飞行艇官方开奖历史记录,168飞艇全国开奖官网直播 幸运飞行艇官方168开奖历史记录查询结果 澳洲幸运5开奖官网开奖结果记录 飞行艇全天计划精准直播-168飞艇官网结果记录查询记录-在线幸运飞行艇168开奖历史记录 澳洲5彩实时官方直播号码|澳洲幸运五开奖结果专属平台 澳洲幸运10 澳洲幸运5开奖结果历史 幸运飞行艇开奖历史查询 幸运飞行艇官网开奖查询 澳洲幸运5-澳洲5开奖记录|幸运五澳洲官网开奖号码查询结果+澳洲幸运5体彩开奖结果