tunnels Archives - Waking up in Geelong https://wongm.com/tag/tunnels/ Marcus Wong. Gunzel. Engineering geek. History nerd. Mon, 14 Oct 2024 23:39:53 +0000 en-AU hourly 1 https://wordpress.org/?v=6.7.1 23299142 Taking a sneak peek at Anzac station https://wongm.com/2024/10/metro-tunnel-anzac-station-open-day/ https://wongm.com/2024/10/metro-tunnel-anzac-station-open-day/#comments Mon, 14 Oct 2024 20:30:00 +0000 https://wongm.com/?p=22546 On the weekend the Metro Tunnel project held a limited public open day for local residents at the recently completed Anzac station, and I was lucky enough to be able to take a look. So let’s head inside! Headed in The open day was held on the closed off section of Domain Road, east of […]

The post Taking a sneak peek at Anzac station appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
On the weekend the Metro Tunnel project held a limited public open day for local residents at the recently completed Anzac station, and I was lucky enough to be able to take a look. So let’s head inside!

Anzac station open day signage on St Kilda Road

Headed in

The open day was held on the closed off section of Domain Road, east of Anzac station.

Future eastbound tram stop on Domain Road

With food stalls.

Food stalls along Domain Road for the Anzac station open day

And kids activities.

Photo frame cutouts at the Anzac station open day

Including a train ride.

'Kids' clarification added to the train signage at the Anzac station open day

But the reason I was there was to see inside Anzac station itself.

Domain Road entrance to Anzac station

Touring the station

We headed downstairs.

Headed down the steps at the Domain Road entrance to Anzac station

The Domain Road entrance having a single up escalator and a flight of stairs.

Single escalator and steps at the Domain Road entrance to Anzac station

As well as a lift, that doubled as a light well.

Lift at the Domain Road end of the unpaid area concourse at Anzac station

We were then greeted by the unpaid area concourse, which passes beneath St Kilda Road.

Domain Road end of the unpaid area concourse at Anzac station

And the tram stop above.

Atrium at Anzac station, bridge linking the two tram stop platforms

A trio of escalators and a lift connect the station concourse to the south end of the tram stop.

Trio of escalators and lift at the southern tram stop entrance to Anzac station

And a single escalator, steps and lift to the northern end.

Single escalator, steps and lift at the northern tram stop entrance to Anzac station

The unpaid area walkway then continued west to the station entrance on Albert Road.

Albert Road end of the unpaid concourse at Anzac station

With a pair of escalators.

Pair of escalators and steps at the Albert Road entrance to Anzac station

Along with a lift.

Lift at the Albert Road entrance to Anzac station

Down to the platforms

Now it was time to head down to the platforms.

Customer service counter and Myki gates at the entrance to Anzac station

Obviously no trains running.

PIDS on the concourse at the Albert Road entrance to Anzac station

But the passenger information screens had been installed.

PIDS outside the main entrance to Anzac station

Through the ticket gates.

Two banks of Myki gates at the exit from the paid area at Anzac station

With sunlight still streaming in from the glass roof above.

Looking out from the paid area towards the atrium at Anzac station

We went past the pair of lifts down to platform level.

Pair of lifts and escalators down to the north end of the platforms at Anzac station

And took the escalators down instead.

Steps and pair of escalators to the north end of the Anzac station platforms

A wide island platform greeting us.

Platform level at Anzac station, looking south

But still no trains.

PIDS on the platform at Anzac station

Temporary fencing in place across the platform screen doors, with a demarcation still in place between active rail tunnels and the under construction railway station.

Temporary fencing in place across the platform screen doors at Anzac station

But network ‘strip maps’ already displayed.

Network 'strip map' for the Sunbury bound platform at Anzac station

Along with customer help points.

Customer help point on the platform at Anzac station

The big orange pendant light fittings also a design feature.

Pendant light fittings at platform level at Anzac station

Along with the orange ceiling details.

Platform level at Anzac station, looking north

It was then time to head back out again, so we took a trio of escalators back to the concourse.

Trio of escalators at the south end of the platform at Anzac station

And then back out of the same ticket gates we entered through.

Two banks of Myki gates at the exit from the paid area at Anzac station

Past the customer service counter.

Customer service counter beside the Myki gates at Anzac station

Past the hidden away back of house area.

Entrance to the back of house area at Anzac station

Back down the unpaid concourse towards Domain Road.

Domain Road end of the unpaid concourse at Anzac station

Back up the escalator.

Escalator and stairs at the Domain Road entrance to Anzac station

And back into the sunlight.

Wayfinding signage at the Domain Road entrance to Anzac station

Ending the tour.

Footnote: a few other things I noticed

Anzac station isn’t completely finished yet – the retail spaces are still taken up by temporary facilities for construction workers.

Temporary staff toilets built into a future retail space on the concourse at Anzac station

With a few bits of wall cladding also missing.

Wall cladding still to be installed along the Domain Road end of the unpaid area concourse at Anzac station

I also noticed a separate set of stairs beside the Domain Road entrance.

Firefighter access stairs beside the Domain Road entrance to Anzac station

Locked away from public use, for firefighter access in case of emergency.

Firefighter access stairs beside the Domain Road entrance to Anzac station

I also found a second lift door hidden away at the back of the Domain Road lift – presumably it leads into the back of house area of the station.

Second lift door to the back of house area at the Domain Road entrance to Anzac station

And on Domain Road the tram tracks have been rebuilt, with new platform stops installed – despite route 58 trams still using the tracks along Toorak Road West they were diverted along back in 2017 to make way for the construction of Anzac station.

Future westbound tram stop on Domain Road

Post retrieved by 35.215.163.46 using

The post Taking a sneak peek at Anzac station appeared first on Waking up in Geelong.

]]>
https://wongm.com/2024/10/metro-tunnel-anzac-station-open-day/feed/ 21 22546
New South Wales coal mines undermining road and rail https://wongm.com/2022/11/coal-mining-nsw-land-subsidence-bridges-railways-tunnel-telephone-cables/ https://wongm.com/2022/11/coal-mining-nsw-land-subsidence-bridges-railways-tunnel-telephone-cables/#comments Mon, 31 Oct 2022 20:30:00 +0000 http://wongm.com/?p=1454 In New South Wales coal mining is big business, with mines hidden beneath ordinary looking forests extracting millions of tonnes of coal each year. However once the coal is removed, an empty void is left behind – and the resulting land subsidence impacts road and rail networks on the surface. This is an incomplete list […]

The post New South Wales coal mines undermining road and rail appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
In New South Wales coal mining is big business, with mines hidden beneath ordinary looking forests extracting millions of tonnes of coal each year. However once the coal is removed, an empty void is left behind – and the resulting land subsidence impacts road and rail networks on the surface.

New and old coal loaders at the South32 operated Dendrobium Mine

This is an incomplete list of infrastructure that has had to be modified, replaced or rebuilt due to underground mining.

A quick introduction to longwall mining

The Total Environment Centre provide us some background to longwall mining in New South Wales.

Longwall mining is a form of underground coal mining where ‘panels’ of coal are mined side by side separated by narrow ‘pillars’ of rock that act as supports.

A long wall panel can be up to 4km long, 250-400m wide and 1-2m thick. Chocks are then placed lines of up to 400m in length to support the roof.

Coal is cut by a machine called a shearer that moves along the length of the face in front of the chocks, disintegrating the coal, which is then taken by a series of conveyors to the surface.

As coal is removed, the chocks are moved into the newly created cavity. As the longwall progresses through the seam, the cavity behind the longwall, known as the goaf, increases and eventually collapses under the weight of the overlying strata.

This collapsing can cause considerable surface subsidence that may damage the environment and human infrastructure.

Longwall mining in NSW began in 1962. In 1983/84 it accounted for 11% of the state’s raw coal production. This had increased to 36% by 1993/94 and stood at 29% in 2003/04.

Nearly all of the coal mined in NSW lies within the Sydney-Gunnedah Basin and in the five defined coalfields of Gunnedah, Hunter, Newcastle, Western (in the Lithgow / Mudgee area) and Southern (in the Campbelltown / Illawarra area).

Virtually all coal mining in the Southern and Western coalfields is underground.

Douglas Park Bridges, Hume Highway

The first example of modified infrastructure I found was the 285 metre long twin Douglas Park Bridges, which carry the Hume Highway 55 metres above the Nepean River.

Douglas Park Bridges over the Nepean River

The concrete piers having a large steel brace attached where they meet the bridge deck.

Added bracing to the Douglas Park Bridges over the Nepean River

The bridge was designed in 1975 by the Department of Main Roads, and did not take land subsidence into consideration, as the Department of Mines indicated mining that they would maintain a coal mining buffer zone around the bridge.

However by the late-1990s approval was given to BHP Coal to expand longwall mining at thier Tower Colliery towards the bridge, provided an extensive monitoring program was put in place.

The impact on the bridge once mining was complete – the abutments were 10 mm closer together, piers had sunk up to 18 mm, and the piers at one end had moved 48.6 mm east.

In the years that followed, the movement in the bridge had worsened, and so in 2007 BHP funded a $9 million project to realign the bridge.

The northern Abutment had moved 57mm, the first Pier around 40mm and the second Pier around 20mm. The next piers were stable.

Because of the different movements, the deck was in a unnatural form and that’s why the bridges had to be realigned. Works had to be proceeded with a minimum of bridge closures.

On the abutments, pot bearings had to be replaced with sliding bearings, which required 4 x 200 tonne jacks to lift the deck. To be able to lift the deck at the Piers, we installed a 40 tonne steel structure to create a lifting base around each Pier.

The realignment was done using 6 x 50 tonne jacks. Once the movement was complete, the bearings had to be welded or clamped to fix the deck to the Piers.

However while this work was still underway, the NSW Government approved further mining was approved beneath the bridge, but this time with a network of 400 sensors collecting deformation data 24 hours a day, along with inclinometers linked to an early warning system.

Trackside solar powered gizmos

Alongside the Melbourne-Sydney railway outside Picton, I found an multiple sets of solar powered instruments connected to the tracks.

Solar powered land subsidence monitoring equipment along the tracks at the down end of Picton

And a few kilometres away outside Douglas Park, I found some more complicated looking systems.

Solar powered land subsidence monitoring equipment along the tracks at the down end of Douglas Park

Complete with fixed structures for the installation of surveying equipment.

Solar powered land subsidence monitoring equipment along the tracks at the down end of Douglas Park

These systems monitor movement in the railway due to mining at the SIMEC Group Tahmoor Colliery and South32 Appin Colliery respectively.

Risk mitigation on the Hume Highway

BHP Billiton Illawarra Coal’s Appin Colliery also passes beneath the Hume Highway at Douglas Park, with land subsidence running the risk of distorting the base of the road pavement. The solution – cutting up the road.

Modelling studies concluded that cutting slots through the existing pavement would be an effective method of dissipating compressive stress in the bound sandstone subbase. As a result of these analyses, the Technical Committee adopted a management strategy where slots would be installed prior to mining.

Sixteen slots were cut in the pavement, eight in each carriageway, directly above the proposed Longwall 703. A further twenty six slots were cut above Longwall 704, for which mining has now started. The spacings of the slots were based mainly on subsidence predictions, with extra slots added within a zone of geological structure.

The Technical Committee recognised that pre-mining slots would probably not be able to accommodate all potential subsidence movements. In particular, irregular subsidence movements could develop, the locations of which could not be identified prior to mining, resulting in locally high compressive stresses in the pavement.

The Technical Committee recognised that additional slots could be installed proactively during mining based on actual monitoring data prior to compressive stresses in the pavement becoming sufficient to result in stepping. Materials, labour and equipment were available to install a new slot within a required 48 hours, with a target to install within 24 hours. This was undertaken on 5 occasions during mining.

Fibre optic sensors were also installed to monitor the movement of the road surface.

BHP Billiton’s Illawarra Coal has embedded three kilometres of fibre optic cables in the Hume Highway to track subsidence caused by a longwall mine that runs under the road.

Illawarra Coal uses fibre Bragg grating sensors to measure temperature and strain at ten-metre intervals along the road’s pavement to detect any forces that could damage the road.

Illawarra Coal’s in-pavement monitoring system is connected to a site-based bank of interrogators that analyse the raw data on a real time basis.

“All data is transferred via wireless network link and is maintained on a web server which is managed by one of the key stakeholders,” a BHP Billiton spokeswoman told iTnews.

“The captured data is compared against pre-determined triggers and has the capability to initiate mobile phone SMS-generated alarms if required for appropriate response as determined by the trigger.”

Replacing a railway tunnel

Just outside of Tahmoor was Redbank Tunnel – a 315 metre long double-track tunnel completed in 1919 as part of the duplication of the Melbourne-Sydney railway.


Google Earth, April 2010

But there was a problem – the nearby Tahmoor Colliery, established in 1975, and expanded in 1994 and 1999.

Looking down on the balloon loop at the Tahmoor Colliery in the Southern Highlands

A further 4.5 million tonnes of coal was located under the tunnel, and Xstrata wanted to expand the mine yet again to extract it, which would destroy the tunnel.

Tahmoor has now undertaken modelling of subsidence impacts on Redbank Tunnel as a result of mining. This modelling has concluded that subsidence impacts would be significant (up to 1130 mm of vertical subsidence) and likely would impact on the structural integrity of the tunnel, resulting in a risk to rail safety on the Main Southern Railway Line which runs through the tunnel.

So their solution – move the railway.

On 21 December 2010, Tahmoor submitted an application to the Department seeking to modify the Minister’s consent (DA 67/98) to allow for mining impacts within Area 3, and thereby to support the proposed mining of these longwalls. In order to avoid the potential impacts on rail safety, Tahmoor proposes to build a major deviation of the Main Southern Railway line for 1.9 km around the tunnel. The modification would also involve construction of a new overbridge to facilitate landowner access to their property once the rail track has been completed.

And decommission the redundant tunnel.

If Redbank Tunnel was left open after it is bypassed, then it is likely that some sections of the Tunnel’s masonry lining would experience cracking, shearing and localised spalling and possible collapses as a result of mining subsidence. Tahmoor therefore proposes to fill the tunnel with material excavated during construction of the proposed deviation, mitigating any potential safety hazards to people who might enter the tunnel and reducing subsidence to the natural surface above the tunnel.

Reshaping the landscape.


Assessment Report: Tahmoor North Mine, Redbank Rail Tunnel Deviation Modification

Work on the deviation commenced in June 2012, with the first train using the new route in December the same year.

Rebuilding a bridge

While chasing trains around Picton, a strange looking bridge caught my eye.

8109 and 8127 departs Picton with an empty aggregate train bound for Peppertree Quarry

The expansion gap looking far too big for the size of the bridge.

Oversized expansion gap in the Bridge Street bridge over the railway at Picton

It turns out coal mining at Tahmoor Colliery was also the driver here.

Tahmoor Coal Pty Ltd is currently replacing an existing bridge over the Main Southern Railway Line near Picton in NSW, due to proposed mining works. The new bridge is located immediately to the west of an existing brick arch bridge. The rail overbridge is an asset of Transport for New South Wales with Wollondilly Shire Council owning the connecting road.

The new overbridge is required because of potential subsidence impacts from scheduled longwall mining activities in the area in late 2015 which would compromise the safety of the existing bridge structure. The project also involves realignment of the road approaches and the demolition of the existing bridge.

A key issue in the design was the articulation of the bridge which had to cater for large opening/closure movements and large differential vertical and horizontal movements between the two ends of the bridge. A large movement modular deck joint and large movement sliding spherical bearings were adopted to accommodate these potentially large mine subsidence displacements.

Construction commenced in June 2015 and was completed by November the same year.

Landbridges on the Hume

This pair of bridges on the Hume Highway outside Mittagong don’t look at unusual from above.


Google Maps

Or from the road.


Google Street View

But they don’t actually span a watercourse.


Google Street View

But were built in 2000s to bridge a section of land affected by mine subsidence.

Plan to bridge the Hume Highway at Mittagong
5 June 2001

Working with the Federal Department of Transport and Regional Services (DOTARS), the Roads and Traffic Authority (RTA) has commenced preliminary work on the upgrading of the Hume Highway on the Mittagong Bypass.

The south and northbound lanes will be re-built and two new three-lane bridges constructed on this major interstate road corridor as a result of geological changes that have damaged the road surface and surrounding region over time.

To maintain travel conditions for the 16,000 vehicles using this section of the highway every day, the RTA will receive an initial $6 million from the Federal Government to complete planning and to construct median cross-over lanes. These will allow traffic to switch between the north and southbound carriageways once construction of the bridges has commenced.

The crossovers will be located near the Nattai River and Gibbergunyah Creek bridges and are expected to take two months to build.

During construction, lane restrictions will be in place in the area from 7am to 6pm Mondays to Fridays and from 8am to 1pm on Saturdays.

“In recent years, engineers have detected a subsidence in the road caused by the unique geology of the area. However, the current rate of ground movement is extremely slow and presents no short-term risk,” an RTA spokesperson said.

“The area has a very complex geological history, including mining activity at the adjacent Mount Alexandra Coal Mine from the 1950s to the 1970s.

“To ensure the highway continues to provide high standard travel conditions, work on the crossovers has commenced, with construction of the bridges expected to begin later in the year for completion by the end of 2002.”

The RTA expects to let a contract for the bridge works in October. The twin three-lane bridges will be supported by concrete pylons sunk 10 metres into the bedrock and protected from possible future earth movement by steel casings.

The southbound bridge will be built first and then operate temporarily as a single carriageway road carrying traffic in both directions during construction of the second bridge.

“The Hume Highway is Australia’s most important interstate road artery, with funding for improvements and maintenance a Federal Government responsibility,” a Department of Transport and Regional Services spokesperson said.

“Accordingly, the cost of the new bridges will be fully funded by the Federal Government.

“Both the Federal Department and the RTA are working to ensure this essential road route is upgraded quickly and with minimal inconvenience to the travelling public.

Telephone trouble at Tahmoor

Even the Telstra network wasn’t safe from mine subsidence at Tahmoor.

As part of the planning for mining longwall LW32, Tahmoor Coking Coal Operations has identified surface assets which may be affected by the mining operation in Tahmoor north area. Some of these assets belong to Telstra and are part of Telstra’s infrastructure in the area.

Telstra’s major assets in the area are: Tahmoor telephone exchange which is located on the north east corner of Thirlmere Way and Denmead Streets and Picton telephone exchange which is Menangle Street.

As mining has continued north of the telephone exchange the potential for impacts on the major network cable infrastructure has changed as now the longwalls are commencing to impact on the Picton telephone exchange area and the optical fibre cables and copper network to the south of Picton.

The planned longwall mining covering the area.


Management Plan – Longwall Mining beneath Telstra plant at Tahmoor and Picton NSW

With the critical parts of the network being:

a. Optical Fibre Cable – this is predominantly due to the nature of the cable in that it is only able to sustain relatively low ground compressive and tensile strains before the external sheath transfers the strain to the individual fibres within the cable. When this occurs the individual fibres have limited capacity to tolerate tensile or compressive strains before they cause interruption to or failure of transmission systems.

b. Aerial Cable – Aerial cable anchored at adjacent poles or from pole to building can be impacted by ground tilt. Where poles are affected by ground tilt the top of the pole can move such that there is a change in the cable catenery with the potential to either stretch the cable or reduce the ground clearance on the particular cable.

And somehow the legacy copper network got off lightly.

Generally the more extensive Main and Local copper cable network is more robust and able to tolerate reasonable levels of mining induced ground strain. The interaction is complex since the network comprises of very small cable of 5mm diameter up to heavily armoured 60mm diameter cables spread diversely across the entire mining area.

Footnote: and the environment

Water being lost to reservoirs.

NSW’s top water agency has called for curbs on two big coal mines in Sydney’s catchment, saying millions of litres of water are being lost daily and that environmental impacts are likely breaching approval conditions.

Cracks in creeks.

The ground is bulging and cracks are reaching from the surface to the coal seam in a section of Sydney’s drinking water catchment that sits above a mine, according to an independent study commissioned by the state government.

Creeks turning orange.

Flows from a “significant” water source for one of Sydney’s dams are turning orange and disappearing beneath the surface because of an underground coal mine that is slated to expand to beneath the reservoir itself.

180 tonnes of concrete pumped into a creek.

It was meant to be a remediation program to repair extensive mine subsidence damage to Sugarloaf State Conservation Area in the Lower Hunter. Instead it turned one environmental disaster into another. Contractors working for coal giant Glencore Xstrata pumped more than 180 tonnes of concrete into a tributary of Cockle Creek at Lake Macquarie.

And yet new mines are approved beneath reservoirs.

The Berejiklian government has given the nod for the extension of coal mining under one of Greater Sydney’s reservoirs, the first such approval in two decades.

The Planning Department earlier this month told Peabody Energy it could proceed with the extraction of coal from three new longwalls, two of which will go beneath Woronora reservoir.

All of this makes a few damaged bridges and cracked highways pale in comparison.

Further reading

Post retrieved by 35.215.163.46 using

The post New South Wales coal mines undermining road and rail appeared first on Waking up in Geelong.

]]>
https://wongm.com/2022/11/coal-mining-nsw-land-subsidence-bridges-railways-tunnel-telephone-cables/feed/ 3 1454
Delivering concrete segments to the Metro Tunnel https://wongm.com/2019/12/melbourne-metro-tunnel-concrete-segments/ https://wongm.com/2019/12/melbourne-metro-tunnel-concrete-segments/#comments Mon, 09 Dec 2019 20:30:00 +0000 https://wongm.com/?p=13826 The tunnel boring machines responsible for digging Melbourne’s Metro Tunnel started work in August 2019, but the concrete segments that will line the new tunnel have had a much longer journey. Their start their life behind an anonymous gate in Ravenhall, next door to the Regional Rail Link tracks. But the ‘tunnel lining segment manufacturing […]

The post Delivering concrete segments to the Metro Tunnel appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
The tunnel boring machines responsible for digging Melbourne’s Metro Tunnel started work in August 2019, but the concrete segments that will line the new tunnel have had a much longer journey.

Site clearance works continue at City Square

Their start their life behind an anonymous gate in Ravenhall, next door to the Regional Rail Link tracks.

Metro Tunnel tunnel lining segment manufacturing facility at Ravenhall

But the ‘tunnel lining segment manufacturing facility’ sign gives it away.

Metro Tunnel tunnel lining segment manufacturing facility at Ravenhall

Overhead cranes travel over the casting yard.

Production started early, so that a stockpile of tunnel lining segments could be built up.

180 segments being poured a day.

The first segments were delivered in August 2019.

Driven across Melbourne six at a time on the back of a semi-trailer.

Semi trailer delivers a load of six precast concrete tunnel segments to the site

Until they arrived at the future North Melbourne station site.

Semi trailer delivers a load of six precast concrete tunnel segments to the site

In September work on the shed over the station box was still underway.

Shed taking shape over the station box

But was completed in October.

Completed shed over the station box for the storage of precast concrete tunnel segments

Ready to store the concrete segments, before they are lowered into the tunnel.

Precast concrete tunnel segments ready to be lowered into the tunnel

Loaded onto a rubber tyred TBM support vehicle.

And driven through the tunnel to the TBM itself.

Which then assembles them into a tunnel wall.

A sidenote on the gantry cranes

The gantry cranes at the casting yard were supplied by Australian manufacturer Eilbeck Cranes, as were cranes at the Melbourne CBD worksites.

Lifting a six sided Calbah Engineering kibble loaded with spoil out of the City Square shaft

Those cranes seem to be more successful than those at Parkville station – dismantled due to safety concerns.

Meanwhile on the West Gate Tunnel

The West Gate ‘Tunnel’ might be predominately surface roads, but it actually features two tunnels: 4 kilometre long outbound and 2.8 kilometre long inbound.

Freeway widening works beside Richards Court in Brooklyn

The precast concrete segments for this project are being manufactured by LS Precast in Benalla, served by a dedicated rail siding.

https://www.youtube.com/watch?v=5pEzo0HCfBY

Post retrieved by 35.215.163.46 using

The post Delivering concrete segments to the Metro Tunnel appeared first on Waking up in Geelong.

]]>
https://wongm.com/2019/12/melbourne-metro-tunnel-concrete-segments/feed/ 3 13826
Melbourne’s rail network emergency response vehicles https://wongm.com/2019/01/melbourne-city-loop-rail-network-emergency-response-vehicle/ https://wongm.com/2019/01/melbourne-city-loop-rail-network-emergency-response-vehicle/#comments Mon, 31 Dec 2018 20:30:00 +0000 http://wongm.com/?p=2584 If something ever goes wrong in Melbourne’s City Loop tunnels, emergency responders need a way to get to the scene of the incident. The first problem Walking along the tracks will take forever – each section of concrete slab track has a hole in the middle! So emergency trolleys were provided at each entrance to […]

The post Melbourne’s rail network emergency response vehicles appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
If something ever goes wrong in Melbourne’s City Loop tunnels, emergency responders need a way to get to the scene of the incident.

Siemens train in the City Loop, waiting for the platform at Flagstaff station to clear

The first problem

Walking along the tracks will take forever – each section of concrete slab track has a hole in the middle!

Signals at the east end of Flagstaff station on the Burnley Loop

So emergency trolleys were provided at each entrance to the loop, ready to be clipped together and then pushed down the tracks.

MURL emergency trolley at the Caulfield Loop portal at Southern Cross

But it’s a long way to push a trolley between stations.

Glow in the dark emergency exit signage in the Northern Loop between Parliament station and the portal

And a better solution

So in 2009 the first motorised Rail Network Emergency Response Vehicles were delivered.


Ambulance Victoria photo

The Department of Transport wrote about the new vehicles in their 2009-10 Annual Report (dead link).

Victoria now has 12 Rail Network Emergency Response Vehicles (RNERVs) located at stations along Melbourne’s underground rail loop and other strategic locations. The vehicles are used in emergencies to ferry emergency personnel and aid to the scene of an incident. Nine of the vehicles were purchased in 2009-10.

To test the vehicle’s capability, a simulated emergency exercise – Exercise Orpheus – was held in April 2010. In the exercise, a major emergency was constructed based on a train stranded between Flagstaff and Melbourne Central Stations. To test their performance and suitability, the response vehicles were sent from both stations, transporting emergency services personnel from Victoria Police, Melbourne Fire Brigade and Ambulance Victoria.

Ambulance Victoria also wrote about their first test run.

Welcome to a training exercise involving Melbourne’s emergency authorities that aims to test their preparedness and response to an attack on major infrastructure.

The recent exercise also tested a mobile platform developed by the Department of Transport that can quickly be assembled, then take emergency workers into the Loop and be used to carry patients to safety. The platform, known as the Rail Network Emergency Response Vehicle, is assembled and operated by members of the Metropolitan Fire Brigade.

‘The Loop presents unique challenges because it is not a road and there are only limited access points, which makes it difficult for paramedics to access,’ said Jon Byrne, from Ambulance Victoria’s
Emergency Management Unit.

‘This new platform had been tested in the rail yards, but this was its first use in a training exercise. We wanted to ensure it could take us there and back, plus bring out patients and we were pleased with the results.’

Each vehicle is stored in a cabinet.

'Rail Network Emergency Response Vehicle' (RNERV) stored in a cupboard at Parliament station

Then moved in pieces to the track.


Ambulance Victoria photo

Bolted together.


Ambulance Victoria photo

And driven along the tracks to the incident site.


Ambulance Victoria photo

Battery powered, the British developed Bance motorised hand trolley weighs 121.75 kg, with the heaviest section weighing 53.5 kg, and capable of carrying 1000 kg of loading at 8 km/h up to 25 km.


R. Bance and Co. photo

Now skyrail

Fast forward to today, and Melbourne now has elevated rail tracks – another difficult to access location.

Life extension EDI Comeng 335M approaches Hughesdale station on a down Pakenham service

But the solution is the same – a portable battery powered trolley.


Rail Express photo

But advanced in technology have seen the weight of the trolley drop, while performance has improved.

In December 2018 Rail Express wrote about this Australian-developed rapid deployment trolley.

Rail equipment manufacturer and distributor Melvelle Equipment has developed a cutting-edge rapid deployment rail trolley, manufactured in Australia and already in use on the busy Melbourne Metro network.

The self-propelled trolley can travel up to 100 kilometres with a full payload of 700 kilograms. At its maximum speed, it can travel up to 80 kilometres.

Despite this impressive range, the machine is just 160 kilograms including batteries, and can be assembled by two people in just three minutes, with no tools required. Four people can assemble the machine in just two minutes.

The machine can be removed from the track in three minutes by two people, or as little as 90 seconds by four people. Its heaviest component weighs just 40 kilograms.

The first units of the trolley were delivered to Metro Trains Melbourne in March 2018.

“The Level Crossing Removal Authority approached us regarding the need to have emergency response vehicles at every train station for the overhead [skyrail] system, because you can’t drive a truck up there,” Melvelle explains.

“The machine is stored at the stations, and if there’s an emergency the responders can wheel it out of the storage area, set it up on track, and travel down the track to the emergency, bringing all their service gear – for example a stretcher – and their people.”

Hand throttle via joystick including horn, traction control, regenerative braking, dead-man pedal, emergency brakes, and full interlocking of all parts of the assembly, meaning if a wheel or a handrail is not correctly installed, the trolley will not move and a light panel will display the location of the error. There are two sets of controls on the trolley, but only one joystick, which must be moved by the operator in order to change direction, up or down the railway.

Melvelle says his company plans to export the product, with interest already registered as far away as UAE and England for the system.

“The trolley is designed manufactured in our factory in Newcastle and I it is the lightest and safest trolley on the market,” he says.

Who said Australian innovation and manufacturing was dead?

Post retrieved by 35.215.163.46 using

The post Melbourne’s rail network emergency response vehicles appeared first on Waking up in Geelong.

]]>
https://wongm.com/2019/01/melbourne-city-loop-rail-network-emergency-response-vehicle/feed/ 2 2584
CityLink’s clever tunnelling technologies https://wongm.com/2015/08/melbourne-city-link-tunnelling-technology/ https://wongm.com/2015/08/melbourne-city-link-tunnelling-technology/#comments Thu, 06 Aug 2015 21:30:43 +0000 http://wongm.com/?p=6122 With all of the recent talk about the construction of the Melbourne Metro rail tunnels beneath Swanston Street and the Yarra River, it seems that many people have forgotten how our last major tunnel project was built - CityLink.

West Gate Freeway at CityLink

The post CityLink’s clever tunnelling technologies appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
With all of the recent talk about the construction of the Melbourne Metro rail tunnels beneath Swanston Street and the Yarra River, it seems that many people have forgotten how our last major tunnel project was built – CityLink.

West Gate Freeway at CityLink

CityLink consists of two tunnels – the shorter Domain Tunnel that carries westbound traffic, and the longer Burnley Tunnel that carries eastbound traffic – with roadheaders being used to construct the majority of each tube. However at each end of the tunnel, the project faced the same problems as the Melbourne Metro tunnels.

At the western end of both tunnels is Grant Street and St Kilda Road, full of both road and tramway traffic.

Grant Street viewed on Google Street View

Here a ‘top down’ methodology was adopted while digging the massive hole.

Excavations for cut  cover works at Grant Street May 1998 (Ian Harrison Hill)
Excavations for cut & cover works at Grant Street May 1998 (Ian Hill, SLV image H99.20/24)

The 2002 book Journey and Arrival: The Story of the Melbourne CityLink published by the Institution of Engineers, Australia elaborates:

The conventional cut-and-cover method was not used at the Grant Street portal, in part to accommodate the impact on the adjacent Victorian College of the Arts (VCA). The size of the excavation necessary for cut-and-cover was huge: 35 metres wide and progressively increasing in depth to about 25 metres at St Kilda Road.

The top-down technique used along Grant Street involved the installation of columns along the alignment of the outer walls of the tunnels, and along the centre line which would ultimately form the barrier between the two tunnels. This was achieved by drilling holes about 900 mm in diameter to bedrock, and then backfilling the holes with concrete. A concrete beam was then constructed along the top of the columns to form the support for the tunnel roof. Once the spans were in place, Grant Street was reinstated and excavation took place unimpeded beneath the deck.

The top-down variation of the cut-and-cover method also reduced the disruption on St Kilda Road, a major thoroughfare with busy tram lines. In fact tram services were closed on only one weekend. The crossing of St Kilda Road was undertaken in stages. Initially the outer service roads were closed and traffic was diverted to the central roadway. This allowed the construction of the columns and tunnel roof in the same manner as along Grant Street. However, extensive propping was necessary under the surface to support the columns against the 25 metre depth of soil pressure. Once work on the outer service roads was completed, traffic was re-diverted to allow work on the central part of the road.

Meanwhile at the east end of the Domain Tunnel was the Yarra River, which passed only a few metres above the future tunnel roof.

Alexandra Avenue viewed on Google Street View

It was decided to build the river crossing in two stages, with a coffer dam being used to keep the water out while allowing the river to keep flowing.

Coffer dam construction in Yarra River for Domain Tunnel 26497 (Ian Harrison Hill)
Coffer dam construction in Yarra River for Domain Tunnel 26/4/97 (Ian Hill, SLV image H99.20/10)

Again, Journey and Arrival: The Story of the Melbourne CityLink gives the technical details:

The construction of the cut-and-cover crossing of the Yarra River represented some of the cleverest engineering of the whole project. Essentially, a trench had to be cut in the riverbed, the tunnel built in it, and the riverbed placed back on top.

As these works could not proceed easily underwater, the river had to be diverted away from the riverbed worksite during construction. The most efficient way to do this, while ensuring minimum disruption to river flows and traffic, was to work on the crossing in two parts: initially shutting off about two thirds of the river from one bank, and, when completed, switching to the other bank, then closing the other third of the river to complete the process.

What does it mean for Melbourne Metro?

Back in April 2015 how to built the Melbourne Metro tunnels beneath the Yarra River was still unresolved – possible solutions being an immersed tube tunnel, or CityLink style cut and cover using a coffer dam.

This week the final solution was announced – a tunnel boring machine would do the work, with the tunnel running to the east of Princes Bridge, around seven metres below the riverbed, and 11 metres below the surface.

More photos of CityLink

The State Library of Victoria holds the ‘Melbourne City Link Project Series‘ – images taken by photographer Ian Hill during the construction of CityLink.

There is a lot more technical details in Journey and Arrival: The Story of the Melbourne CityLink – I’ve just scraped the surface in this post.

VicRoads also have an interesting CityLink related document on their website – Exhibit I Project Scope and Technical Requirements.

Post retrieved by 35.215.163.46 using

The post CityLink’s clever tunnelling technologies appeared first on Waking up in Geelong.

]]>
https://wongm.com/2015/08/melbourne-city-link-tunnelling-technology/feed/ 13 6122
How deep are Melbourne’s City Loop tunnels? https://wongm.com/2013/08/melbourne-city-loop-rail-tunnel-depth/ https://wongm.com/2013/08/melbourne-city-loop-rail-tunnel-depth/#comments Mon, 26 Aug 2013 21:30:32 +0000 http://wongm.com/?p=3182 Melbourne's City Loop - if you racing to catch a train from the lowest level of Parliament station, it feels like you are taking a journey to the centre of the earth. But how deep are the stations in reality?

Climbing out of Parliament station

The post How deep are Melbourne’s City Loop tunnels? appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
Melbourne’s City Loop – when racing to catch a train from the lowest level of Parliament station, it feels like a journey to the centre of the earth. But how deep are the stations in reality?

Climbing out of Parliament station

The City Loop consists of four tunnels over two levels: platforms 1 and 2 on the upper deck serve the lines through Clifton Hill and Caulfield, while platforms 3 and 4 on the lower deck serve the lines that pass through Burnley and North Melbourne.

The process

Unfortunately detailed diagrams of each City Loop station aren’t accessible online, which rules out the obvious way to read the depth measurement. Firing up the GPS on your phone could be another way, but getting a fix on the satellites from underground is impossible, and even if you could – the altitude accuracy of a consumer GPS device is about +/- 15 meters!

I ended up turning to another set of diagrams – the railway issued ‘Grades and Curves’ book that shows the general alignment and elevation for each of the City Loop tunnels. (the full set of diagrams can be found at Vicsig)

City Loop grades and curves diagram

The diagrams in the ‘Grades and Curves’ book are used to assist train drivers in learning the routes they will be driving along – trains don’t accelerate and stop like a car, so knowing about sharp curves, long inclines and steep descents is essential to keep the train under control.

Unfortunately the Grades and Curves diagrams only include elevation in metres above the Low Water Mark – a datum set as the level reached by seawater at low tide – and not in metres below the surface!

To determine the ground level elevation of each station, I turned to the survey marks database operated by Land Victoria. It gives the elevation of thousands of survey points around Australia, all given in relation of the Australian Height Datum (AHD) – a height set to the mean sea level for 1966-1968 calculated at thirty tide gauges around the coast of the Australian continent.

With the depth of each platform given by the Grades and Curves diagrams, the ground level elevation from survey marks, and the the rest is just simple arithmetic.

Flagstaff Station

Escalators at Flagstaff - three of the four banks only have 2 escalators and a set of stairs

For Flagstaff station the Grades and Curves diagram states the upper level is at +8 metres LWM, and the lower level is at -1 metres LWM. William Street is at the crest of the hill, so survey mark ‘MELBOURNE NORTH PM 50 MURLA’ (#308300500) on nearby Little Lonsdale Street can be used, located at a height of 28.446 metres above AHD.

Datum Calculated
Surface level +28.446 metres AHD
Rail level, upper platforms +8 metres LWM
Depth, upper platforms 20.5 metres
Separation between platforms 9 metres
Rail level, lower platforms -1 metres LWM
Depth, lower platforms 29.5 metres

Melbourne Central Station

Escalators from the Melbourne Central concourse down to platform 3/4

For Melbourne Central station the Grades and Curves diagram states the upper level is at +2 metres LWM, and the lower level is at -7 metres LWM. La Trobe Street is a complicating factor – the Swanston Street end being higher than than that at Elizabeth Street – so I looked at two survey marks – ‘MMB 380’ (#450003801) on the Elizabeth Street corner is at 13.450 metres above AHD, while mark ‘MMB 388’ (#450003881) is located at a height of 22.370 metres above AHD.

Datum Calculated
Surface level +13.450 / +22.370 metres AHD
Rail level, upper platforms +2 metres LWM
Depth, upper platforms 11.5 / 20.5 metres
Separation between platforms 9 metres
Rail level, lower platforms -7 metres LWM
Depth, lower platforms 20.5 / 29.5 metres

Parliament Station

Collins Street concourse at Parliament station platform 1/2

For Parliament station the Grades and Curves diagram states the upper level is at +7 metres LWM, and the lower level is at -3 metres LWM. Spring Street is relativity flat atop the station, so I used survey mark ‘MELBOURNE NORTH PM 16 MURLA’ (#308300160) on Lonsdale Street, located at a height of 36.746 metres above AHD.

Datum Calculated
Surface level +36.746 metres AHD
Rail level, upper platforms +7 metres LWM
Depth, upper platforms 29.5 metres
Separation between platforms 10 metres
Rail level, lower platforms -3 metres LWM
Depth, lower platforms 39.5 metres

So what have I discovered?

  • Parliament station is the deepest below ground (39.5 metres) on the City Loop
  • Melbourne Central is the furthest station below sea level, but is the closest to the surface (between 20.5 and 29.5 metres) due to Elizabeth Street being in a valley
  • Flagstaff station is the highest station above sea level, but is the second deepest (29.5 metres) due to the location atop a hill

Checking my answers

After doing the maths myself, I remembered that the Metropolitan Transport Authority put together a booklet of City Loop facts and figures in the mid-1980s.

It quotes the following depths:

  • Parliament station: 40 metres
  • Flagstaff station: 32 metres
  • Melbourne Central station: 22 / 29 metres

I was out by 3 metres for the depth of Flagstaff station, but for the other locations, my roundabout way of determining the City Loop depth was reasonably accurate!

An alternate method

Another method to measure the depth of an underground station is to measure the height of an escalator step, count the total number of steps between platform level and the surface, and multiply them together to get the total height.

Post retrieved by 35.215.163.46 using

The post How deep are Melbourne’s City Loop tunnels? appeared first on Waking up in Geelong.

]]>
https://wongm.com/2013/08/melbourne-city-loop-rail-tunnel-depth/feed/ 10 3182