Off-peak services and the Metro Tunnel

Ever since the Metro Tunnel was first announced, the big question has been “how many trains will they actually run through it off-peak”. Well, there still isn’t an answer to it, but the 2022 Melbourne Airport Rail business plan does give some hope that it’s something more than the pitiful service currently provided on the Sunbury line.

'More trains across Melbourne' banner outside the City Square site

Some background

Early government media releases used generic language such as:

“This project will create space to run more trains, more often, right across Melbourne. We’re getting it done.” said Premier Daniel Andrews.

As well as:

“We know these changes will be disruptive but we need to get on and build the Metro Tunnel – so we can deliver the frequent, reliable, turn-up-and-go transport system passengers need.” said Minister for Public Transport Jacinta Allan.

The only hard figures being an increase in peak capacity.

'More trains in and out of the city' poster outside the City Square construction site

And the Melbourne Metro Program “Business Case Baseline” document dated February 2016 showing half of off-peak trains terminating at West Footscray.

HCMT set 26 stopped at West Footscray platform 2 on the up

Leaving Sunshine as a station where V/Line services outnumber ‘Metro’ ones.

But those pathetic sounding numbers didn’t actually reflect the service that the government intended to provide through the Metro Tunnel – a spokesperson ringing up blogger Daniel Bowen and telling him it was just a “base case” and not a service plan – which just left us all in the dark as to what the Metro Tunnel would deliver.

But is this it?

In September 2022 the Victorian Government published the Melbourne Airport Rail business case, with a 296 page main report, and a 413 pages of appendices.

Melbourne Airport Rail propaganda wall still in place at Metro Tunnel HQ for now

And on page 11 of the appendices is what we’ve all been waiting for – a proposed service specification for the Metro Tunnel.

The assumed service specification of each option is summarised in the tables below. Note these assumed service specifications are for the purpose of comparing the options only. All changes to the Base Case under each option are highlighted orange.

The number of trains due to use the Metro Tunnel before the opening of the Melbourne Airport line.

Peak Hour Peak 2-hour Interpeak Offpeak
West Corridor 18 36 12 12
Sunbury 6 12 3 3
Watergardens 6 12 3 3
Sunshine 3 6 3 3
West Footscray 3 6 3 3
Airport 0 0 0 0
East Corridor 18 36 12 12
Pakenham 9 18 3 3
Clyde 9 18 3 3
Westall 0 0 6 6

And after the Melbourne Airport line has been completed.

Peak Hour Peak 2-hour Interpeak Offpeak
West Corridor 18 36 12 12
Sunbury 6 12 3 3
Watergardens 6 12 3 3
Sunshine 0 0 0 0
West Footscray 0 0 0 0
Airport 6 12 6 6
East Corridor 18 36 12 12
Pakenham 9 18 3 3
Clyde 9 18 3 3
Westall 0 0 6 6

So if the above is to be believed, the Sunbury line is in line for a massive off-peak service increase once the Metro Tunnel opens:

  • Sunbury – twice as many trains, from every 40 minutes to every 20 minutes,
  • Watergardens – twice as many trains, from every 20 minutes to a ‘turn up and go’ 10 minute frequency,
  • Sunshine – three times as many trains, with a ‘turn up and go’ 10 minute frequency, with three more trains slotted in between,
  • West Footscray – four times as many trains, with one every 5 minutes.

And once Melbourne Airport line opens, things will become even better – the Sunshine and West Footscray shortworkings will be extended through to Melbourne Airport, providing a 5 minute off-peak frequency to the Sunbury line as far as Sunshine.

Now we just need to hope that this is what actually gets delivered!

A public–private partnership for pothole repairs

All across Victoria potholes are a common sight, as finding for basic repairs has been funneled away for grand traffic congestion inducing projects like the West Gate Tunnel. But there is one exception – a few roads in Melbourne that were upgraded as part of the ‘Western Roads Upgrade’ project. So why are they different?

Road maintenance vehicle at work on Anderson Road, Sunshine - one of the roads upgraded by Netflow under the Western Roads Upgrade public private partnership

The Western Roads Upgrade

The $1.8 billion Western Roads Upgrade project was launched in 2018 and completed in 2021.

And included upgrades to eight arterial roads in Melbourne’s west.

A93 signage on Forsyth Road northbound approaching Old Geelong Road

Massive new intersections.

Upgraded intersection at Boundary Road and Palmers Road

And the resurfacing of 260 km of existing roads between Footscray to Werribee.

Transdev bus #168 BS03KR on route 903 heads past roadwork on Wright Street, Sunshine

So why haven’t these roads fallen apart in the years that have followed?

It’s because the upgrade was delivered part of a convoluted public–private partnership between the Department of Transport and Planning and a private consortium called ‘Netflow’, which sees the government give them buckets of money for the next 20 years to maintain the road, with a compliance regime that will penalise them for as little as a pothole.

To manage these contractual obligations, you need data – so the Netflow consortium has a fleet of inspection vehicles continually doing laps of the western suburbs.

Road surface inspection vehicle heads along Wright Street, one of the roads upgraded by Netflow under the Western Roads Upgrade public private partnership

Covered in LiDAR sensors looking for faults in the road surface.

Road surface inspection vehicle heads along Wright Street, one of the roads upgraded by Netflow under the Western Roads Upgrade public private partnership

And maintenance crews in ‘Western Roads Upgrade’ branded vans ready to swoop in and fix faults ASAP.

Road maintenance vehicle at work on Anderson Road, Sunshine - one of the roads upgraded by Netflow under the Western Roads Upgrade public private partnership

Their marketing blurb describing it as:

Netflow is transforming the way road maintenance is performed in Victoria, using real-time data on the condition of the network to employ maintenance strategies that minimise disruption and maximise whole-of-life value.

This more efficient maintenance program is resulting in an average of one road per week being resurfaced.

The core of Netflow’s whole-of-life maintenance solution is the central Network Delivery Hub.

The 24/7 hub monitors the performance of the network in real time, providing a seamless interface with the Department of Transport, local councils and other third parties to implement dynamic-scheduled works, keep communities informed, predict and prevent issues, and coordinate timely responses to incidents.

The use of vehicle-mounted street scanning technology, drones, 3D modelling and physical inspections allow Netflow to schedule preventative maintenance and reduce road closures.

This whole-of-life approach provides best-in-class maintenance of the road network at a lower cost.

Meanwhile for every other road in Victoria, the government just keeps kicking the can down the road, because they aren’t accountable to anyone.

So why not keep doing it

If the Western Roads Upgrade project was so successful in getting rid of potholes, why doesn’t the government do more upgrades like this? Turns out the private companies behind it lost money by underbidding.

The Andrews government’s $1.8 billion Western Roads Upgrade has stalled after a key subcontractor walked off the job with just $920 remaining in its accounts, leaving other subcontractors millions of dollars out of pocket.

The Sunday Age can also reveal the head contractor on the project, South-African headquartered and Perth-based WBHO, has reported $133 million in losses after it admitted to under-bidding to win the work, and its executive chairman, Louwtjie Nel, conceded the project was the company’s “biggest error in 50 years”.

WBHO’s main subcontractor, little known western suburbs-based civil engineering firm Civilink, quit in August and has gone into liquidation, owing creditors at least $13 million.

And so the tender process on the South Eastern Roads Upgrade Project and Northern Roads Upgrade Project were terminated in July 2020 – replaced by the $2.2 billion Suburban Roads Upgrade to be delivered as 12 individual projects by a pre-qualified panel in an approach modelled on the Level Crossing Removal Project.

Footnote: digging into the legalese

The full details of the public–private partnership can be found in the “Outer Suburban Arterial Roads Program – Western Package” Project Deed.

For a start, look at the corporate structure.

Minister for Roads and Road Safety on behalf of the Crown in right of
the State of Victoria
(State)

Netflow OSARS (Western) Pty Ltd as trustee for Netflow OSARS (Western) Unit Trust for and on behalf of the Netflow OSARS (Western) Partnership and Cintra OSARS (Western) Pty Ltd as trustee for Cintra OSARS (Western) Unit Trust for and on behalf of the Netflow OSARS (Western) Partnership (Project Co)

And it’s contractors, investors and financiers all the way down.

D&C contractor

The D&C contractor is WBHO Infrastructure Pty Ltd. Project Co has appointed the D&C contractor to design and construct the eight Arterial Road Upgrades and the Initial Rehabilitation Works.

Significant subcontractors

The D&C contractor has appointed the following significant subcontractors to deliver elements of the Arterial Road Upgrades:
• Ace Infrastructure Pty Ltd;
• Civilex Victoria Pty Ltd; and
• Winslow Constructors Pty Ltd

Contracts with other subcontractors are expected to be executed shortly.

Equity investors

The following entities have committed to provide the equity required for Project Co:
• Plenary Investments (Western OSARS) Pty Ltd
• Cintra OSARs Western Ltd

Financiers (long term)

The following entities have provided the long term debt required for the Project:
• DB Life Insurance Co. Ltd.
• Pensionskasse Des Bundes Publica
• Samsung IFM Global Infrastructure Debt Professional Investment Private Investment Trust No. 1
• Manulife Asset Management (Hong Kong) Limited
• Teachers Insurance and Annuity Association of America

Financiers (short term)
The following entities have committed to provide the short term debt required for the Project:
• Westpac Banking Corporation
• Bank of China Limited
• Mizuho Bank, Ltd
• Industrial and Commercial Bank of China Limited

VicRoads gives this as their justification for completing the upgrade as a public–private partnership.

A range of procurement options that are typically considered for high-value road construction projects were assessed based on their suitability and value for money drivers in reference to the specific characteristics of the Western Roads Upgrade. The following four procurement options were shortlisted on the basis that they represented models currently in use and have a history of utilisation by VicRoads or other State agencies:

  • design and construct;
  • alliance;
  • design, build and maintain; and
  • design, build, finance and maintenance (availability-based PPP).

Following a procurement options assessment of the shortlisted procurement options, the availability based PPP delivery model was the highest ranked procurement option. This option was recommended, and subsequently approved by the State, for delivery of the Project.

The key considerations in recommending an availability-based PPP model are summarised below.

  • The model provides increased opportunity for the State to harness private sector innovation and structure a contract that incentivises whole-of-life efficiencies to arterial road investment.
  • The bundling of construction and maintenance tasks under a long-term agreement (subject to vigorous competition) can drive efficiency in delivery and asset management. Introducing private finance also provides additional discipline and scrutiny of risk (for example, financier due diligence and oversight). The PPP model can also be expected to deliver improved and more consistent road asset conditions under a PPP commercial structure involving an appropriate KPI and abatement regime.
  • On a ‘whole-of-life’ cost comparison basis, PPPs have been documented to deliver better value for money outcomes as compared to traditional contracting delivery methods (separate, unbundled contracts) and have been successfully deployed across a range of sectors (including roads) in Victoria. These benefits are not only limited to cost savings but also include improved and more consistent road asset conditions. A focus on longer term, ‘whole-of-life’ contracting also incentives private sector innovation in terms of how best to maintain the asset over the term in the most cost effective and efficient manner.

Prior to the release of an invitation for EOI, a market sounding of the relevant industry, including sponsors, contractors, road maintenance providers and financiers, was undertaken. The feedback from this process supported the State’s selection of a PPP model to deliver the Project and achieve the State’s objectives.

Along with a calculation of the ‘Public Sector Comparator’ that they used to argue that a PPP saved the government money.

The Public Sector Comparator is an estimate of the hypothetical, risk adjusted, whole-of-life cost of the Project if delivered by the State. The PSC is developed in accordance with the output specification and risk allocation proposed for the private sector party arrangement and is based on the most likely and efficient form of conventional (that is, non-PPP) delivery by the State.

The PSC is expressed in terms of the net present cost (NPC) to the State, calculated using a discounted cash flow method taking full account of the costs and risks that would arise through State delivery. The PSC includes amounts for the design and construction of Arterial Road Upgrades and Initial Rehabilitation Works, as well as maintenance and lifecycle and other costs during the Maintenance Phase of the Project.

The PSC is made up of a number of elements as contained in Table 7.

Components of the PSC NPC ($millions)
Arterial Road Upgrades and Initial Rehabilitation Works (construction costs) $ 622
Maintenance and lifecycle costs $ 438
Raw PSC $ 1,060
Transferred risk $ 100
Proposal Comparable PSC $ 1,160

The quantitative value for money assessment, as demonstrated by the estimated savings between the Proposal Comparable PSC and the final Proposal is shown in Table 8.

Public Sector Comparator
(NPC – $millions)
$ 1,160
Final Proposal (NPC– $millions) $ 1,133
Estimated savings (%) 2.3%

Something much easier to understand is the scope – divided up into three objectives:

Arterial Road Upgrades (ARU)

The design, construction and financing of eight ARUs in Melbourne’s west during the Initial Phase, consisting of:

• The duplication of Dunnings Road between Point Cook Road and Palmers Road and the duplication of Palmers Road between Dunnings Road and Overton Road;
• The duplication of Palmers Road between Overton Road and Boundary Road and Robinsons Road between Boundary Road and the Western Freeway including the realignment of Palmers Road across Sayers Road;
• The duplication of Derrimut Road between Sayers Road and Dohertys Road;
• The duplication of Leakes Road between Fitzgerald Road and Derrimut Road;
• The duplication of Dohertys Road between Fitzgerald Road and Grieve Parade;
• The duplication of Dohertys Road between Foundation Road and Palmers Road;
• The duplication of Forsyth Road between Old Geelong Road and Wallace Avenue, including the re-alignment of Forsyth Road and Old Geelong Road; and
• The replacement of the existing Duncans Road Bridge over the Princes Freeway West and the addition of westerly (or Geelong) orientated ramps.

Initial Rehabilitation Works

Improvement works on road pavements and structures within the Maintenance Network during the Initial Phase to meet service standards.

Maintenance Services

Delivery of maintenance and lifecycle services (routine and periodic) within the Maintenance Network during the Maintenance Phase.

As are the key performance indicators Project Co is required to meet.

The KPIs set out in the KPI Summary of this Annexure B are separated into 7 categories, being:
1. Inspections;
2. Response;
3. Compliance;
4. Pavement performance;
5. Structures performance;
6. Reporting; and
7. Safety.

Which then explodes into an enormous level of detail regarding the Project Scope and Delivery Requirements (PSDR).

1.1 Hazard Inspection
During the Maintenance Phase, Project Co must ensure that safety inspections are carried out in accordance with the safety inspections requirements set out in the Code of Maintenance Standards.

1.2 Defect Inspection
During the Maintenance Phase, Project Co must ensure that inspections are carried out in accordance with the defect inspections requirements set out in the Code of Maintenance Standards.

1.3 Structure Condition Inspection
During the Maintenance Phase, Project Co must ensure that inspections are carried out in accordance with the condition inspections requirements set out in section 8.2(b)(i)(B) of Part F7 and section 8.3(b)(ii) of Part F7 of the PSDR and the Code of Maintenance Standards.

2.1 Hazard Response
During the Maintenance Phase, Project Co must ensure that the hazard response, from the time Project Co identifies a hazard by inspection or receives notification from the State or VicRoads of a hazard to the time the hazard is rectified by Project Co, is compliant with the requirements set out in the Code of Maintenance Standards.

2.2 Defect Response
During the Maintenance Phase, Project Co must ensure that the Defect response, from the time Project Co identifies a Defect by inspection or receives notification from the State or VicRoads of a Category A and/or a Category B Defect to the time the Defect is rectified by Project Co.

2.3 Emergency Response
During the Maintenance Phase, Project Co must ensure that the emergency response, from the time Project Co receives notification from the State or VicRoads of an Emergency Event to the time the Emergency Event is responded to by Project Co.

3.1 Code of Maintenance Standards
During the Maintenance Phase, Project Co must ensure that all activities (to the extent not already captured under KPI items 1.1, 1.2, 1.3, 2.1, 2.2 and 2.3) set out in the Code of Maintenance Standards, under items RM411 to RM416 and RM611 to 613 and RM 615 identified in the Table 750.H11 -Routine Maintenance Intervention Criteria and Response are completed in accordance with the requirements set out in the section 7 of Part F7 of the PSDR.

3.2 Forecast Maintenance and Refurbishment Plan
During the Maintenance Phase, Project Co must ensure that all activities set out in the Forecast Maintenance and Refurbishment Plan are completed in accordance with that plan (as updated and reviewed by the State in accordance with the Review Procedures on an annual basis to reflect the condition monitoring of Project Assets).

3.3 Communications and Community Relations Plan During the Maintenance Phase, Project Co must ensure that all activities set out in the Communications and Community Relations Plan are completed in accordance with that plan.

And into the gory details of road surface quality.

4.1 Roughness – Network based
During the Maintenance Phase (Initial), Project Co must ensure roughness limits set out in section 8.2(a)(ii) of Part F7 of the PSDR, are as a minimum achieved for pavement on the Project Roads.

4.2 Rutting – Network based
During the Maintenance Phase (Initial), Project Co must ensure rutting limits set out in section 8.2(a)(iii) of Part F7 of the PSDR, are as a minimum achieved for pavement on the Project Roads.

4.2.1 Rutting – Pavement Reporting Section based
During the Maintenance Phase (Full) an individual KPI Incident will occur for each 100m lane section of any Pavement Reporting Section failing to meet these requirements as set out in section 8.3(a)(iii)(B) of Part F7 of the PSDR.

5.1 Structures Performance
During the Maintenance Phase (Initial) in relation only to Existing Structural Assets, Project Co must ensure that Existing Structural Assets are operating at their designed load, speed, and availability levels with no restrictions applied, in accordance with the requirements set out in section 8.2(b)(i)(A) of Part F7 of the PSDR.

Submitting paperwork.

6.1 Asset Management System Availability
During the Maintenance Phase, Project Co must ensure the Asset Management System is available to the State and VicRoads, in accordance with the requirements set out in section 1 of Part D of the PSDR.

7.1 General Reporting
During the Initial Phase, Project Co must submit Monthly Development Phase Progress Reports and the Monthly Maintenance Phase Performance Reports in accordance with the Deed.

And finally – Safety.

8.1 Safety
During the Initial Phase and Maintenance Phase, an individual Safety KPI Incident is an Event for incidents which result in a Lost Time Injury (LTI), Total and Permanent Disability or Fatality to any employee, or contractor, or consultant of Project Co or its contractors or sub-contractors in connection with the performance of the Services or Works.

at least they’ve created a lot of email jobs along the way.

A history of nine car long V/Line trains

I realised the other day I’ve never written a complete piece about the history of V/Line operating nine car long trains – so here goes.

VLocity VL74 leads VL21 and VL57 on a 9-car down Wyndham Vale service at Ravenhall

In the beginning

The story starts back in December 2005, with the introduction of the VLocity trains to the V/Line fleet. Each set consisted of two carriages seating a total of 140 passengers, with a drivers cab at each end. For the peak hour express trains on the Geelong line, they would coupled together three units to make a six car train.

VLocity VL01 leads two classmates on an up Geelong express service at Corio

We then saw a politically motivated 20% cut in V/Line fares in 2007, resulting in an explosion in patronage, especially on the Geelong line.

One response to this was the ordering of additional trains for V/Line, who saw their first three-car long VLocity set enter service in August 2008.

3VL41 heads back to Melbourne at North Shore

But with patronage still growing and suburban and V/Line trains sharing the tracks out of Melbourne, running more services on the Geelong line wasn’t an option. But V/Line had another solution – 7-car long VLocity train, made up of two 2-car sets with a 3-car set.

7 car VLocity consist approaches South Geelong on an up empty cars run from Marshall

These trains were introduced to the Geelong line in November 2008 and ran until June 2015, when Geelong trains commenced using the new Regional Rail Link tracks, and the last of the 2-car VLocity trains had been extended to be three cars along.

VLocity VL16 and classmate depart Tarneit on a down Geelong service

So what next?

As early as 2011 V/Line knew longer trains would be required – their ‘Initial Strategic Operations Plan’, obtained by the Greens under the Freedom of Information Act, says the following:

V/Line anticipates that by this point in time (2018) a high capacity style DMU will be required for Geelong services. It is expected that these trains would operate in 8- or 9-car consists and would each be able to carry 750 – 800 customers. It is expected that the eight peak hour services would be operated with the high capacity DMUs.

And the Regional Rail Link project also included provision for these longer trains – providing 250 metre long platforms at Footscray, Tarneit and Wyndham Vale stations to cater for a hypothetical nine car long train, made up of three 3-car sets.

'VL9' - nine-car VLocity set stopping mark on the RRL platform at Footscray

But for some unknown reason, they decided only only build a 190 metre long platform at Sunshine, despite plenty of space at the city end for a 250 metre long one.

Trio of trains at Sunshine: pair of V/Line services outnumber the single Alstom Comeng

But in 2016 the State Government’s focus switched to a ‘high capacity next generation regional train’ – from the PTV website:

High capacity next generation regional trains

The 2016-17 State Budget includes $10 million in development funding for High-Capacity Next Generation Regional Rolling Stock to cater for the future needs of regional Victoria.

A next generation high capacity regional train will be commissioned in the coming years to cater for strong patronage growth and provide new peak services.

With V/Line saying in 2017 that nine car trains are possible, but won’t be happening any time soon – from the Geelong Advertiser.

Nine-carriage V/Line trains possible, but no plans for Geelong line yet
23 October 2017

The boss of the regional rail network has admitted for the first time nine-carriage trains on the Geelong line are a possibility.

Potential for a mega-train carrying more than 660 passengers comes after calls from commuters and rail experts to reduce peak-time overcrowding on the line.

But while James Pinder said a nine-carriage train was possible, he said it was not a current priority.

Mr Pinder said V/Line’s priority was bolstering its fleet from three to six-carriage trains.

“The (VLocity) train is capable of running in a nine-car configuration. (To run nine-carriage trains) it becomes an issue around infrastructure and number of vehicles (available),” he said.

“We don’t currently have any plans to run nine-car ser­vices. To run large numbers of nine-car services we would have to have a look at (increasing) platform lengths.”

On Monday, a spokeswoman for the Public Transport Minister did not say if the Government was considering introducing nine-carriage trains on the regional network.

The Geelong Advertiser under­stands platforms at Geelong station are long enough for nine-carriage trains — which could open the possibility for Geelong to Melbourne express trains.

Platforms at other smaller stations on the line would need to be extended for a stopping-all-stations Waurn Ponds to Southern Cross train.

Mr Pinder said nine-­carriage trains did not run across the V/Line network at present.

And they finally happen

On Sunday 21 June 2020 V/Line ran their first nine car VLocity train on the mainline, taking it from Southern Cross Station to Wyndham Vale and back to test their operation, as well as platform clearances.

VLocity VL07 leads the 9-car test train through Ravenhall on the down

Sunshine station being the sticking point.

VLocity VL23 pulls up at the very end of Sunshine platform 3

The last one and 1/2 carriages fouling the junction when the front was stopped at the city end of platform 3.

The last one and a 1/2 carriages of the 9-car test train overhang platform 3 at Sunshine

Or sticking out in front after the rear of the train was brought onto the platform.

The train has shunted forward, and now the first one and a 1/2 carriages of the train overhang platform 3 at Sunshine

These tests were then followed in July 2021 by more testing, this time between Ballarat and Lal Lal, which doesn’t see any V/Line passenger services run along it.


ThebusofdoomFSX video

But it took another year for the first nine car train to take passengers – following the 30 May 2022 timetable change.

Passengers in Melbourne’s west now have more space on selected peak services with 9-car VLocity trains running to and from Wyndham Vale Station for the first time.

The longer trains, which have the highest-capacity of any regional commuter train in Victoria, will boost capacity by 50% cent on the busiest part on the V/Line network.

The new 9-car services will run each weekday, with 1 in the morning peak starting at Wyndham Vale and 2 in the evening peak departing from Southern Cross.

As well as improving capacity, the 9-car trains also provide more doors for boarding, reducing crowding in corridors particularly in peak periods.

Platforms will also be extended at Sunshine Station to allow nine-car VLocity trains to stop there in the future.

But due to the short platforms, these nine car services had to run express through Sunshine, as well as Deer Park.

Extending the platforms at Sunshine

With level crossing removal works at Deer Park station regularly closing the Geelong and Ballarat lines, V/Line took the opportunity to finally extend the platforms at Sunshine. In March 2023 the piled foundations were installed.

New piled foundations in place for the up end extension of Sunshine platform 3

The real work kicking off in April, with assembly of the steel platform supports.

Steel platform edge panels waiting to be installed at Sunshine platform 3

And pouring of the concrete deck.

Steel deck in place at Sunshine platform 3 and 4, concrete pour now underway

They then left the completed section of platform fenced off for a month.

Extended platform 4 mostly complete, still fenced off and lacking tactile paving

The nine car trains still having to skip the stop.

VLocity VL23 trails two classmates on an up 9-car VLocity service from Wyndham Vale  express through Sunshine

Until May, when they decided to take down the fence between new and old.

VLocity VL105 arrives into Sunshine on a down South Geelong service

And the introduction of a new timetable from 28 May 2023 adding a stop at Sunshine to the nine car Wyndham Vale services.

However in recent months I haven’t seen a nine car train run – possibly due to a shortage of VLocity railcars following the retirement of the H set locomotive hauled carriage fleet.

Carriage set SSH22 at the up end of the three 6-car sets stored at Echuca

And so they choose to cut down a nine car train to six cars, than a six car train to three.

And now to Melton?

In May 2021 the State Government announced that funding would be provided to allow nine car VLocity trains to run to Melton, a promise repeated in October 2022.

VLocity VL108 and classmate on a down Wendouree service overtake VL60 waiting in the platform at Melton

And reiterated yet again in March 2024.

The Melton level crossing removal works will help introduce larger nine-car VLocity trains as part of the $650 million Melton Line Upgrade, increasing capacity for passengers by 50 per cent and creating 1,000 jobs during construction – while making roads safer and less congested for pedestrians.

To support the introduction of nine car trains, a new train stabling facility is being investigated at Cobblebank where trains could be stored when they are not operating, further supporting local jobs in construction and ongoing maintenance.

But look at what else was happening at the same time – a brand new station at Deer Park was opened in April 2023, with platforms only 215 metres long – half a carriage (10 metres) too short!

VLocity VL90 and classmate arrive into the new elevated Deer Park station on the up

That flew under the radar until August 2024, when the State Opposition gave a media drop to the Herald Sun, and then it was all over the news.

Footnote: it’s not just platform length

The new platform extensions at Sunshine also happen to be ~100mm higher than the existing platforms.

The new platform extensions are ~100mm higher than the existing platforms

This happens to be a new platform height standard, which was also used at Deer Park station – and happens to be incompatible with the outward swinging plug doors fitted to V/Line’s Sprinter railcars.

Freshly refurbished Sprinter 7004 leads 7002 through Deer Park on an up test run from Geelong

And so those trains are banned from stopping at the new platforms.

Photos from ten years ago: August 2014

Another instalment in my photos from ten years ago series – this time it is August 2014.

Regional Rail Link

Yes, more Regional Rail Link this month! First off, a V/Line train headed over the newly upgraded North Melbourne flyover bound for Southern Cross, avoiding the suburban trains down below.

P14 climbs towards the North Melbourne flyover with a push-pull service bound for Southern Cross

The sharp curves catching V/Line unaware a few years later, when almost the entire VLocity train fleet was withdrawn from service due to wheel wear issues.

At Footscray the upgraded station was open to passengers, with the forecourt to Irving Street nicely landscaped.

Completed forecourt on Irving Street to the west of the station

And restoration work underway on the heritage listed station buildings.

Restoration works underway to the station building on platform 6

There were also works happening in the background – a new traction power substation was under construction, so that extra suburban services could use the track capacity freed up by giving V/Line trains their own route into the city.

New structure being built between the Newport bound tracks for a traction power upgrade

But despite the infrastructure upgrades, little use was made of the extra capacity – by 2018 only half of the extra capacity was being used.

And still on the trains

I photographed a slice of the past out at Beaconsfield, where the 1950s-era overhead wiring and traction power tie station was still in place. It’s all since been replaced by a modern power supply as part of the work to support the rollout of High Capacity Metro Trains to the Pakenham line.

Beaconsfield tie station: traction feeders and equipment hut

At Flagstaff station I found a set of defective myki gates under repair – presumably from being smashed open by a fare evader.

Pair of defective myki gates under repair at Flagstaff station

While over at Southern Cross were Authorised Officers in their new military-style vests, looking out for the next person trying the same trick.

Authorised Officers in their new military-style vests

On the trams

A decade ago City Circle trams were still in the maroon and gold livery, and the ‘shard’ at Federation Square had yet to be demolished for the Metro Tunnel entrance.

W6.981 westbound at Flinders and Swanston Street

The original Z1 class trams were also still running down Swanston Street, with only two doors per side and dinky little sliding windows.

Z1.35 heads north at Swanston and Bourke Streets

East Preston Depot was still open to serve the high floor B2 class trams used on route 11 and 86 – all since replaced by the low floor E class trams based out of ‘New’ Preston Depot.

Track fan leading towards the shed at East Preston Depot

While testing of the new E class trams was still continuing – I found one at the route 57 terminus in West Maribyrnong on a late night test run.

E.6010 departs the route 57 terminus at West Maribyrnong

Meanwhile on Collins Street, things were going backwards – passengers having to step up to trams from street level.

Trams use a temporary stop while platform resurfacing works are completed at Collins and Swanston Street

The platform stops closed so they could be dug up and raised to current standards, despite only being a decade old.

Resurfacing the Town Hall platform stop at the corner of Collins and Swanston Street

Buses

Transdev had taken over from National Bus, but the transition into the new PTV colour scheme was going in fits and starts.

Transdev bus #556 rego 5944AO with the PTV 'shard' livery partially applied

While route 286 through the back streets of Blackburn was removed, but then a few months later, reintroduced as route 271.

Disused bus stops in Blackburn, following the removal of the route 286 bus

Another changed bus stop can be found at Melbourne Airport – the route 901 service to Broadmeadows and eventually Frankston once stopped outside Qantas terminal T1.

Transdev #660 waiting at the route 901 stop at Melbourne Airport

But these days it’s hidden at the far end of the ‘Ground Transport Hub’, a long walk from terminal 4.

And something different

My next stop at Melbourne Airport a decade ago was Brisbane.

IMU165 arrives at Domestic station on the Brisbane Airport rail link

Catching a train from Brisbane Airport into the city.

Waiting for a cross at International station, with a Domestic-bound service arriving in the other platform

To Roma Street – the Brisbane Transit Centre since demolished for the Cross River Rail project.

Looking across the Brisbane Transit Centre above Roma Street station

While I was in town, I photographed some of their first generation EMU trains.

EMU78 passes EMU60 at South Brisbane station

The Merivale Bridge.

6-car SMU set crosses the Merivale Bridge

And buses on the network of Brisbane City Council operated busways.

Brisbane Transport bus C2037 at the Cultural Centre busway station

Which include underground bus stations.

Bus picks up passengers at the underground King George Square busway station

Passengers boarding buses from air conditioned platforms.

Down on the air conditioned platforms at the King George Square busway station

But the reason for my visit was a trip on The Sunlander.

Locomotive 2152 still leading the train at Townsville

A locomotive hauled sleeping train that ran from Brisbane to Cairns until December 2014.

Washbasin and visitors seat inside a roomette carriage

When I woke up the next day, we were well into cane country.

Cane train shunting loaded wagons at Helens Hill

But the trip north is a long one – not arriving into Cairns until that evening.

 Locomotives 2414 and 2152 run around the empty train at Cairns

While in Cairns I rode the Skyrail Rainforest Cableway up to Kuranda, and with some lucky timing spotted a Kuranda-bound train stopped at Barron Falls.

Looking over Barron Falls to the railway on the other side of the gorge

After lunch, it was time to head to Kuranda station, where I found a signal box still in service.

Inside the signal box at Kuranda

And caught the Kuranda Scenic Railway back down the range to Cairns.

Passengers look out over Barron Falls from the station platform

Unfortunately I didn’t have time for the four day journey on the Savannahlander, but I did see it arrive back into Cairns.

This week railcar 2028 made the four day journey from Cairns and Forsayth and back

But it was time to fly home via Sydney – my plane passing over the Hawkesbury River railway bridge on our descent.

Looking down on the Hawkesbury River railway bridge

The Inner West Light Rail

Urbos 2 LRV in the Transport for NSW livery, crossing the Wentworth Park viaduct in Lilyfield

And a Pacific National container train shunting the freight yard at Cooks River.

8173 shunting container wagons at Cooks River yard

Time to change planes, and soon enough I was back in Melbourne – greeted at the airport luggage claim by propaganda for the Napthine Government’s East West Link, CityLink Tulla Widening, and an unfunded Melbourne Airport Rail Link.

Government propaganda at Melbourne Airport spruiking unfunded transport projects

A decade on we’ve gotten the west half of the East West Link, the Tullamarine Freeway has been widening, and airport rail – still talking.

Footnote

Here you can find the rest of my ‘photos from ten years ago‘ series.

Nine car trains and the short platform at Deer Park

Over the weekend a year blog post of mine got a mention in the Herald Sun – the subject being the new railway station at Deer Park and the platforms not quite long enough to fit a nine car V/Line train.

VLocity VL90 and classmate arrive into the new elevated Deer Park station on the up

The story starts

Opposition transport spokesman and part time gunzel Matthew Guy kicked off the topic with a video posted to Instagram, detailing how the newly built platforms at Deer Park station were 10 metres short of a nine car VLocity train.

Liberal Party HQ also sending a media drop over to the Herald Sun, who published it on Sunday 18 August.

As well as a comment from the opposition transport spokesman who tipped the newspaper off to the topic.

To add to the confusion and frustration, a Freedom of In-formation request by the opposition seeking documents on the nine-car train plan was refused due to the fact it was an “unfunded future project”. The nine-carriage trains, which come in sets of three carriages, are 225m long, and Sunshine station was recently upgraded from 190m to 225m to allow them to stop there. But Deer Park station, re-built during the $234m Mt Derrimut level crossing removal, is only 215m.

Look at who else got a mention.

The oversight was spotted on rail documents by self-described “train nut” Marcus Wong, who described it on his transport blog as a “comedy of errors”.

The blog post in question being my piece “First day at the new Deer Park station” from May 2023.

Herald Sun cartoonist Mark Knight also drew the short platform in cartoon form for Tuesday 20 August edition.

On the ground at Deer Park

The new platforms at Deer Park are longer than a 6-car VLocity train, with plenty of empty platform beyond the back of the train.

VLocity VL103 and VL23 pause at the new elevated Deer Park station on the down

But it turns out they aren’t actually long enough for the 9-car trains currently used on services to Wyndham Vale to stop at.

VLocity VL07 leads the 9-car test train through Ravenhall on the down

The new platforms are only 215 metres long – half a carriage (10 metres) too short!

So why can’t they be longer?

The western end of Deer Park station is located hard up against a brand new townhouse development.

New station towers over preserved grasslands at Deer Park

The townhouses almost touching the retaining wall that supports the tracks.

Three storey townhouse development peeks over the noise walls on the new elevated track

So there is no room for the platforms to be any longer at that end.

Emergency exit stairs used to link platform 1 to the streets north of the station

But what about the city end?

VLocity VL104 arrives into Deer Park on a down Geelong service

Here the platforms end right where the reinforced earth embankment that the station is built atop also end.

Bus loop runs beneath the viaduct at the up end of the station

The tracks transitioning to the precast concrete u-trough viaduct.

Transition to U-trough viaduct at the up end

So why didn’t they make the viaduct a little bit shorter, so that the platform could be made a little big longer?

Pedestrian crossing links the southern station entrance to the bus interchange

Personally I don’t know – possibly if they made the viaduct one span shorter, the bus interchange wouldn’t be long enough for the “one stop per bus route, no matter how infrequently it runs” rule PTV follows.

PTV liveried Kinetic bus #228 BS06OR departs Deer Park station with the shuttle to Caroline Springs

Or the longer station would have taken up space for car parking down at ground level, and “no net loss of car parking” is the one rule that level crossing removals always follow.

Completed car park on the south side of the station

Footnote: the other Deer Park platform problem

The new platform at Deer Park was also built to a new platform height standard, which isn’t compatible with V/Line’s Sprinter trains.

OPERATING RESTRICTION – DEER PARK STATION
SPRINTER RAILCARS

Upon advice from V/Line Network Engineering, Sprinter Railcars will NOT be permitted to stop at Deer Park Station at KP 17.943.

Any Sprinter Railcars travelling towards/from Wyndham Vale and Geelong or Melton and Bacchus Marsh will be required to run express through Deer Park Station.

The Operating Restriction will apply until further advised due to clearance issues between the Sprinter Railcar and the new Platform when the doors are in the Open position.

You can read about that saga here.

Engineers check the clearances between the modified plug doors fitted to Sprinter 7014 and a wheelchair ramp on the raised platform at Deer Park